#Project CodeProject NameDepartmentDistrictPhaseProgress StatusApprove Date
     
28261IWD/Watham Leirak/110Impvt. of Watham LeirakPWDImphal-West---Completed
28262IED/5 culvert-Porompat road/199Constn. of 5(five) culvert around Porompat Road No. 2PWDImphal-East2ndcompleted
28263IED/Ural Chiru/275M/o Ural Chiru IVRPWDImphal-EastNaCompleted
28264IED/Keithelmanbi-Moirangpurel/336Improvement of Road from Keithelmanbi to MoirangpurelPWDImphal-East1stCompleted
28265IED/Sanjenbam-Gouranagar (1-4 km)/253Impvt. of approach road from Sanjenbam to Gouanagar vice -versa Gouranagar to Mahadeva Repater Stattion (Baruni) from 1.00 Km to 4.00 KmPWDImphal-East1stCompleted
28266IED/Sanjenbam-Gouranagar (11-14 km)/256Impvt. of approach road from Sanjenbam to Gouanagar vice -versa Gouranagar Mahadeva Repeater Station (Baruni) from 11.00 Km to 14.00 KmPWDImphal-East3rdcompleted
28267IED/Sanjenbam-Gouranagar (11-14 km)/256Impvt. of approach road from Sanjenbam to Gouanagar vice -versa Gouranagar Mahadeva Repeater Station (Baruni) from 11.00 Km to 14.00 KmPWDImphal-EastIIICompleted
28268UKL/Eastern Ring/42Improvement of eastern ring road from New District Hospital to Hungpung High School 0-10 kmPWDUkhrulPhase lConstruction
28269UKL/Eastern Ring/42Improvement of eastern ring road from New District Hospital to Hungpung High School 0-10 kmPWDUkhrulPhase lConstruction
28270UKL/Shiroi/44Improvement of road from NH-202 junction to Shiroi.PWDUkhrulPhase lConstruction in progress
28271MSPCLA3Contruction of 2 nos. of 400 kV line bay at Imphal Power Grid Sub-Station, YurembamPOWER (MSPCL)Imphal-WestXyz100 %
28272IED/Epum Road/372Impvt. of Epum Road (Northern side) connecting with Imphal-Saikul roadPWDImphal-East1stCompleted
28273MANIDCO_C&I_26CONSTRUCTION OF M/S MAHI NUNGBI POTTERY CENTRE AT NUNGBI KHULLEN UKHRUL DISTRICT MANIPUR Trade Commerce and IndustriesUkhrulPHASE-IIn progress
28274MANIDCO_C&I_26CONSTRUCTION OF M/S MAHI NUNGBI POTTERY CENTRE AT NUNGBI KHULLEN UKHRUL DISTRICT MANIPUR Trade Commerce and IndustriesUkhrulPHASE-IIn progress
28275EE/BPR/Maint. of side berm from Toubul Bazar/Maint. of Side Berm from Toubul Bazar to Pattaba.PWDBishnupur1stin progress
28276HSD/Keishampat Mutum Leirak/15Improvement of Keishampat Mutum Leirak, IVR connecting Kangabam Leikai to Thiyam Leikai, Leimajam Leikai PYDC to Khwairakpam Leikai culvert i/c connecPWDImphal-West1Completed
28277HSD/Keishampat Mutum Leirak/15Improvement of Keishampat Mutum Leirak, IVR connecting Kangabam Leikai to Thiyam Leikai, Leimajam Leikai PYDC to Khwairakpam Leikai culvert i/c connecPWDImphal-West1Completed
28278HSD/Kodompokpi Mamang Hentak Khongban Road/14Improvement of Kodompokpi Mamang Hentak Khongban Road, Hiyangthang Awang Leikai Leftout Portion, Hiyangthang Palak road, Malom Khoiromtaba and MongshaPWDImphal-West1Completed
28279HSD/Kodompokpi Mamang Hentak Khongban Road/14Improvement of Kodompokpi Mamang Hentak Khongban Road, Hiyangthang Awang Leikai Leftout Portion, Hiyangthang Palak road, Malom Khoiromtaba and MongshaPWDImphal-West1Completed
28280H&SC/NEC-MFCEstablishment of Model Floriculture Centre at Litan, Ukhrul District, Sendra, Bishnupur District and Panam Garden, Andro, Imphal East DistricHorticulture & Soil ConservationOthersFINAL PHASEOn going