1 | SP/23-D3/ManipurCollege(MCR)-IW | Upgradation of Mini Conference Room at Manipur College, Imphal West, Manipur. | Education (S) | Imphal-West | final | Completed | 03/07/2025 |
2 | SP/23-D3/ManipurCollege(MCR)-IW | Upgradation of Mini Conference Room at Manipur College, Imphal West, Manipur. | Education (S) | Imphal-West | final | Completed | 03/07/2025 |
3 | SP/23-D3/ManipurCollege(MCR)-IW | Upgradation of Mini Conference Room at Manipur College, Imphal West, Manipur. | Education (S) | Imphal-West | final | Completed | 03/07/2025 |
4 | SP/23-D3/ManipurCollege(MCR)-IW | Upgradation of Mini Conference Room at Manipur College, Imphal West, Manipur. | Education (S) | Imphal-West | final | Completed | 03/07/2025 |
5 | KMJ/Impvt of Phungyar to Loushing/274 | Impvt of road from Phungyar to Loushing Village (approx. 5Km) - Kamjong Divn | PWD | Kamjong | Phase II | 90% | 03/07/2025 |
6 | KMJ/Impvt of Phungyar to Loushing/274 | Impvt of road from Phungyar to Loushing Village (approx. 5Km) - Kamjong Divn | PWD | Kamjong | Phase II | 90% | 03/07/2025 |
7 | KMJ/Impvt of Phungyar to Loushing/274 | Impvt of road from Phungyar to Loushing Village (approx. 5Km) - Kamjong Divn | PWD | Kamjong | Phase II | 90% | 03/07/2025 |
8 | KMJ/Impvt of Phungyar to Loushing/274 | Impvt of road from Phungyar to Loushing Village (approx. 5Km) - Kamjong Divn | PWD | Kamjong | Phase II | 90% | 03/07/2025 |
9 | KMJ/Impvt of Phungyar to Loushing/274 | Impvt of road from Phungyar to Loushing Village (approx. 5Km) - Kamjong Divn | PWD | Kamjong | Phase II | 90% | 03/07/2025 |
10 | KMJ/Impvt of Phungyar to Loushing/274 | Impvt of road from Phungyar to Loushing Village (approx. 5Km) - Kamjong Divn | PWD | Kamjong | Phase II | 90% | 03/07/2025 |
11 | KMJ/Impvt of Phungyar to Loushing/274 | Impvt of road from Phungyar to Loushing Village (approx. 5Km) - Kamjong Divn | PWD | Kamjong | Phase II | 90% | 03/07/2025 |
12 | KMJ/Impvt of Phungyar to Loushing/274 | Impvt of road from Phungyar to Loushing Village (approx. 5Km) - Kamjong Divn | PWD | Kamjong | Phase II | 90% | 03/07/2025 |
13 | UKL/SE-IV/Dungrei to NH102A via Sacred Hea/43 | Blacktopping of from Dungrei Junction to National Highway 102A via Sacred Heart Hr Sec School | PWD | Ukhrul | Phase 1 | 94.1% | 03/07/2025 |
14 | BD-I/NLU | Land Development for National Law University | PWD | Imphal-East | phase I | work in progress | 03/07/2025 |
15 | BD-I/NLU | Land Development for National Law University | PWD | Imphal-East | phase I | work in progress | 03/07/2025 |
16 | BD-I/NLU | Land Development for National Law University | PWD | Imphal-East | phase I | work in progress | 03/07/2025 |
17 | BD-I/NLU | Land Development for National Law University | PWD | Imphal-East | phase I | work in Progress | 03/07/2025 |
18 | BD-I/NLU | Land Development for National Law University | PWD | Imphal-East | phase I | work in progress | 03/07/2025 |
19 | BD-I/NLU | Land Development for National Law University | PWD | Imphal-East | phase I | work in progress | 03/07/2025 |
20 | BD-I/NLU | Land Development for National Law University | PWD | Imphal-East | phase I | work in progress | 03/07/2025 |