| 22161 | TBL/Darpan/Plan/46 | Construction of Wall Fencing and internal approach road with drain and land development in the temporary office at the D.C. Kakching. | PWD | Kakching | 3rd& final | 100% | 16/03/2020 |
| 22162 | TBL/Darpan/Plan/46 | Construction of Wall Fencing and internal approach road with drain and land development in the temporary office at the D.C. Kakching. | PWD | Kakching | 3rd& final | 100% | 16/03/2020 |
| 22163 | IWD/North Kangla Gate/149 | Restoration of Norther Kangla gate to Khuyathong | PWD | Imphal-West | 1 | Completed | 16/03/2020 |
| 22164 | TBL/Darpan/Plan/46 | Construction of Wall Fencing and internal approach road with drain and land development in the temporary office at the D.C. Kakching. | PWD | Kakching | 3rd& final | 100% | 16/03/2020 |
| 22165 | 19/41/2018/MNRE(SSL/LMP)/MANIKREDA(CCpur) | LED Solar Street light | MANIREDA | Churachandpur | Phase1 | Installed | 16/03/2020 |
| 22166 | 19/41/2018/MNRE(SSL/LMP)/MANIREDA(Moirang) | LED SOlar street light in Moirang | MANIREDA | Bishnupur | Phase1 | Installed | 16/03/2020 |
| 22167 | 19/41/2018/MNRE(SSL/LMP)/MANIREDA(Moirang) | LED SOlar street light in Moirang | MANIREDA | Bishnupur | Phase1 | Installed | 16/03/2020 |
| 22168 | 19/41/2018/MNRE(SSL/LMP)/MANIREDA(Moirang) | LED SOlar street light in Moirang | MANIREDA | Bishnupur | Phase1 | Installed | 16/03/2020 |
| 22169 | 19/41/2018/MNRE(SSL/LMP)/MANIREDA(Moirang) | LED SOlar street light in Moirang | MANIREDA | Bishnupur | Phase1 | Installed | 16/03/2020 |
| 22170 | 19/41/2018/MNRE(SSL/LMP)/MANIREDA(Moirang) | LED SOlar street light in Moirang | MANIREDA | Bishnupur | Phase1 | Installed | 16/03/2020 |
| 22171 | 19/41/2018/MNRE(SSL/LMP)/MANIREDA(Moirang) | LED SOlar street light in Moirang | MANIREDA | Bishnupur | Phase1 | Installed | 16/03/2020 |
| 22172 | 19/41/2018/MNRE(SSL/LMP)/MANIREDA(Moirang) | LED SOlar street light in Moirang | MANIREDA | Bishnupur | Phase1 | Installed | 16/03/2020 |
| 22173 | MANIDCO_C&I_31 | CONSTRUCTION OF COMPOUND FENCING OF DIC/ACTC (WESTERN & SOUTHERN SIDE), POROMPAT, DIC, IMPHAL EAST | Trade Commerce and Industries | Imphal-East | Phase1 | Completed | 16/03/2020 |
| 22174 | MANIDCO_C&I_31 | CONSTRUCTION OF COMPOUND FENCING OF DIC/ACTC (WESTERN & SOUTHERN SIDE), POROMPAT, DIC, IMPHAL EAST | Trade Commerce and Industries | Imphal-East | Phase1 | Completed | 16/03/2020 |
| 22175 | ND/ROAD/Taosang-Lubanglong/8 | Construction of road from Taosang to Lubanglong. | PWD | Noney | 1st phase | 80% | 16/03/2020 |
| 22176 | ND/ROAD/Taosang-Lubanglong/8 | Construction of road from Taosang to Lubanglong. | PWD | Noney | 1st phase | 80% | 16/03/2020 |
| 22177 | ND/ROAD/Taosang-Lubanglong/8 | Construction of road from Taosang to Lubanglong. | PWD | Noney | 1st phase | 80% | 16/03/2020 |
| 22178 | CCP/K. Salbung-Kholnom/79 | Improvement of road from NH-2, K. Salbung to Kholnom | PWD | Churachandpur | 2018-19 | Complete | 16/03/2020 |
| 22179 | CCP/M. Songgel- Khomun/78 | Improvement of road from M. Songgel to Khomun road via Tuibong TD Block Office | PWD | Churachandpur | Completed | 2018-19 | 16/03/2020 |
| 22180 | ND/ROAD/Taosang-Lubanglong/8 | Construction of road from Taosang to Lubanglong. | PWD | Noney | 1st phase | 80% | 16/03/2020 |