| 22121 | BITE/15-Tipaimukh-CCpur | Construction of Block Institute of Teacher Education (BITE) Building at Tipaimukh, Churachandpur District, Manipur | Education (S) | Churachandpur | Nil | Work has been completed | 14/02/2020 |
| 22122 | BITE/15-Tipaimukh-CCpur | Construction of Block Institute of Teacher Education (BITE) Building at Tipaimukh, Churachandpur District, Manipur | Education (S) | Churachandpur | Nil | Work has been completed | 14/02/2020 |
| 22123 | BITE/15-Tipaimukh-CCpur | Construction of Block Institute of Teacher Education (BITE) Building at Tipaimukh, Churachandpur District, Manipur | Education (S) | Churachandpur | Nil | Work has been completed | 14/02/2020 |
| 22124 | SCERT/15-BITE-SEN | Construction of Block Institute of Teacher Education at Kangpokpi, Senapati District | Education (S) | Senapati | Nil | Work has been completed | 14/02/2020 |
| 22125 | EE /BPR/Impvt. of Old Cachar 47 -74/65 | Impvt. of Old Cachar road 47 to 74 Km | PWD | Bishnupur | Phase 1 | In progress | 14/02/2020 |
| 22126 | EE/BPR/Impvt. of rd from Lamdan to Khoupum/64 | Impvt. of road from Lamdan to Khoupum | PWD | Bishnupur | Phase1 | In progress | 14/02/2020 |
| 22127 | EE/BPR/Impvt. of rd from Lamdan to Khoupum/64 | Impvt. of road from Lamdan to Khoupum | PWD | Bishnupur | Phase1 | In progress | 14/02/2020 |
| 22128 | EE/BPR/Impvt. of rd from Lamdan to Khoupum/64 | Impvt. of road from Lamdan to Khoupum | PWD | Bishnupur | Phase1 | In progress | 14/02/2020 |
| 22129 | MID-NESIDS(FDR)-2019-20-Kharkhola | Re-Construction of Pick-up Weir a/c Haipi stream at Kharkhola. | Minor Irrigation Department | Kangpokpi | 1 | Ongoing | 14/02/2020 |
| 22130 | MSPCLB3 | INSTALLATION OF 2x12.5 MVA, 132/33 kV S/S AT MOREH WITH ASSOCIATED 132 kV LINE AND RELATED CIVIL WORK | POWER (MSPCL) | Chandel | xyz | 100 | 13/02/2020 |
| 22131 | MSPCLB3 | INSTALLATION OF 2x12.5 MVA, 132/33 kV S/S AT MOREH WITH ASSOCIATED 132 kV LINE AND RELATED CIVIL WORK | POWER (MSPCL) | Chandel | xyz | 100 | 13/02/2020 |
| 22132 | MSPCLB3 | INSTALLATION OF 2x12.5 MVA, 132/33 kV S/S AT MOREH WITH ASSOCIATED 132 kV LINE AND RELATED CIVIL WORK | POWER (MSPCL) | Chandel | Ongoing | Ongoing | 13/02/2020 |
| 22133 | TML/Road/CJM Court/4 | Improvement of CJM road at District Head Quarter at Tamenglong | PWD | Tamenglong | phase-2 | work in progress | 13/02/2020 |
| 22134 | TML/Road/CJM Court/4 | Improvement of CJM road at District Head Quarter at Tamenglong | PWD | Tamenglong | phase-2 | completed | 13/02/2020 |
| 22135 | TML/Road/CJM Court/4 | Improvement of CJM road at District Head Quarter at Tamenglong | PWD | Tamenglong | phase-2 | work in progress | 13/02/2020 |
| 22136 | TML/Road/CJM Court/4 | Improvement of CJM road at District Head Quarter at Tamenglong | PWD | Tamenglong | phase-2 | work in progress | 13/02/2020 |
| 22137 | TML/Road/CJM Court/4 | Improvement of CJM road at District Head Quarter at Tamenglong | PWD | Tamenglong | phase-2 | work in progress | 13/02/2020 |
| 22138 | TML/Road/CJM Court/4 | Improvement of CJM road at District Head Quarter at Tamenglong | PWD | Tamenglong | phase-2 | work in progress | 13/02/2020 |
| 22139 | TML/Road/CJM Court/4 | Improvement of CJM road at District Head Quarter at Tamenglong | PWD | Tamenglong | phase-2 | work in progress | 13/02/2020 |
| 22140 | TML/Road/CJM Court/4 | Improvement of CJM road at District Head Quarter at Tamenglong | PWD | Tamenglong | phase-2 | work in progress | 13/02/2020 |