9821 | MSPCLB4 | INSTALLATION OF 2x12.5 MVA, 132/33 kV S/S AT HUNDUNG WITH ASSOCIATED 132 kV LINE AND RELATED CIVIL WORKS AT HUNDUNG IN MANIPUR | POWER (MSPCL) | Ukhrul | 5021.39 | 0 | Others | 29/08/2017 | 2012-2013 | Project Status |
9822 | MSPCLC6 | Installation of 2x5 MVA, 33/11 kV Sub-Station at Mayangkhang | POWER (MSPCL) | Senapati | 963.12 | 0 | NEC | 29/08/2017 | 2015-2016 | Project Status |
9823 | MSPCLC5 | Installation of 2x5 MVA, 33/11 kV Sub-Station with associated 33 kV line at Nungbi Khullen | POWER (MSPCL) | Ukhrul | 1449.83 | 0 | NLCPR | 29/08/2017 | 2014-2015 | Project Status |
9824 | MSPCLC4 | Installation of 2x2.5 MVA, 33/11 kV Sub-Station at Kasom Khullen with associated 33 kV line and related civil work | POWER (MSPCL) | Ukhrul | 1042.26 | 0 | State Plan | 29/08/2017 | 2014-2015 | Project Status |
9825 | MSPCLC3 | Installation of 2x5 MVA, 33/11 kV Sub-Station Power House Site of Loktak Down Stream HEP | POWER (MSPCL) | Bishnupur | 1483.82 | 0 | NEC | 29/08/2017 | 2013-2014 | Project Status |
9826 | MSPCLB3 | INSTALLATION OF 2x12.5 MVA, 132/33 kV S/S AT MOREH WITH ASSOCIATED 132 kV LINE AND RELATED CIVIL WORK | POWER (MSPCL) | Chandel | 11924.00 | 0 | NLCPR | 29/08/2017 | 2014-2015 | Project Status |
9827 | MSPCLB2 | INSTALLATION OF 2x12.5 MVA, 132/33 kV S/S AT THANLON WITH ASSOCIATED LINE | POWER (MSPCL) | Churachandpur | 14238.00 | 0 | NLCPR | 29/08/2017 | 2014-2015 | Project Status |
9828 | IED/New Kaina Road/20 | Improvement of New Kaina Road (Thambalnu Market to Kaina temple) (3 Km length) | PWD | Imphal-East | 340.08 | 0 | State Plan | 28/08/2017 | 2015-2016 | Project Status |
9829 | IED/Andro Road/19 | Improvement of Andro Road from Km 0.00 to Km 12.00 (12 Km. length) | PWD | Imphal-East | 908.77 | 0 | State Plan | 28/08/2017 | 2015-2016 | Project Status |
9830 | IFCD-FCW-17 | Construction of retaining wall on RCC bore pile at U/S of Minuthong Bridge, Imphal River LBB | Water Resources Department (WRD) | Imphal-East | 42.00 | 0 | State Plan | 27/08/2017 | 2017-2018 | Project Status |
9831 | TBL/darpan/tourist/kwm/5 | Improvement of Khongjom Tourist Complex | PWD | Thoubal | 798.00 | 359.88 | Others | 25/08/2017 | 2017-2018 | Project Status |
9832 | TBL/darpan/tblcourt/4 | Construction of G+3 Annexe building for the Court of District & Sessions Judge at Thoubal | PWD | Thoubal | 1555.97 | 1356.49 | CSS / CPS | 25/08/2017 | 2017-2018 | Project Status |
9833 | TBL/darpan/tblcourt/3 | Construction, Renovation and repairing of the District & Sessions Court Buildings, Thoubal | PWD | Thoubal | 171.30 | 137.04 | CSS / CPS | 25/08/2017 | 2017-2018 | Project Status |
9834 | TBL/darpan/rrs/wangbal/2 | Strengthening & Modernisation of Rice Research Station, Wangbal | PWD | Thoubal | 2100.00 | 1745.34 | State Plan | 25/08/2017 | 2017-2018 | Project Status |
9835 | BPR/INA-COMPLEX/1 | Development of INA Complex, Moirang | PWD | Bishnupur | 537.49 | 487.49 | Others | 25/08/2017 | 2014-2015 | Project Status |
9836 | PD/EAP/Sports-Univ/2017 | Construction of Helipad, Meeting Venue, Impt. of road and barricading for laying of Foundation Stone of the National Sports University. | PWD | Imphal-West | 350.00 | 0 | State Plan | 22/08/2017 | 2017-2018 | Project Status |
9837 | JNIMS/Skill Lab. | Construction of Skill Lab. at 6th Floor of Medicine ward at J.N institute of Medical Sciences, Porompat. | PWD | Imphal-East | 140.00 | 100.00 | Central Sector | 22/08/2017 | 2017-2018 | Project Status |
9838 | Soibam/2nd Floor 42 | Construction of 2nd floor Building No. 42 at 25-Soibam Leikai for accommodation of JNIMS Nursing Hostel, JNIMS. | PWD | Imphal-East | 16.53 | 0.00 | State Plan | 22/08/2017 | 2017-2018 | Project Status |
9839 | Soibam/32-58 | Construction of Building Nos. 32, 36, 37, 44, 53 & 58 located at Soibam Leikai for accommodation of JNIMS staff. | PWD | Imphal-East | 77.20 | 0.00 | State Plan | 22/08/2017 | 2017-2018 | Project Status |
9840 | JNIMS/150resident | Construction of 150 Capacity Resident Doctor's(Boys) Hostel at J.N. Institute of Medical Sciences, Porompat, Imphal. | PWD | Imphal-East | 2610.82 | 1100 | State Plan | 22/08/2017 | 2017-2018 | Project Status |