Progress
 
 
Project Details
DAR-2018-000679
RMSA/15-CDL-MACHI-GH
Construction of Girls Hostel i/c Septic Tank and Soak pit under RMSA 2013-14 of Machi, Chandel District.
2015-03-28
Education (S)
Chandel
168.50
168.47
RMSA
Completed
Nil
24.500295513513425,94.07564229011075
Construction of Girls Hostel i/c Septic Tank and Soak pit under RMSA 2013-14 of Machi, Chandel District. (Sh: (i) Construction of Underground R.C.C. Water Sump & (ii) Construction of Surface Water Tank)
Progress Update : 2022-11-22
Completed
Nil
so5.eew
24.500295513513425,94.07564229011075
24.50048002,94.07594325
0.036716477338145
Approved
2022-12-23 10:45:12
ee1.eew
0
Surface water tank1

Progress Update : 2022-11-22
Completed
Nil
so5.eew
24.500295513513425,94.07564229011075
24.50039705,94.07562114
0.011490932619129
Approved
2022-12-23 10:45:31
ee1.eew
0
Underground water sump

Progress Update : 2022-11-22
Completed
Nil
so5.eew
24.500295513513425,94.07564229011075
24.50053741,94.0759172
0.038692046918056
Approved
2022-12-23 10:45:48
ee1.eew
0
Surface water tank3

Progress Update : 2021-11-20
Completed
Nil
sur1.eew-mn
24.500295513513425,94.07564229011075
24.5003202,94.0758098
0.017169082800879
Approved
2022-03-25 11:07:59
ee1.eew
0
Room

Progress Update : 2021-11-20
Completed
Nil
sur1.eew-mn
24.500295513513425,94.07564229011075
24.5004695,94.0755801
0.02034310403783
Approved
2022-03-25 11:07:47
ee1.eew
0
Internal portion verandah

Progress Update : 2021-11-20
Completed
Nil
sur1.eew-mn
24.500295513513425,94.07564229011075
24.5005541,94.0755563
0.030039539336727
Approved
2022-03-25 11:07:15
ee1.eew
0
Front view

Progress Update : 2020-06-30
Work has been completed
Nill
kh1.eew-mn
24.500295513513425,94.07564229011075
24.5004888,94.075749
0.024050846248851
Approved
2020-07-02 10:27:23
ce.eew-mn
0
Front view

Progress Update : 2018-04-04
In-progress (roof level)
Nil
sur1.eew-mn
24.500295513513425,94.07564229011075
24.5004183,94.075285
0.038642054989399
Approved
2018-04-10 11:04:39
ce.eew-mn
0
Construction work for the building is in progress upto roof level. (front view)

Progress Update : 2018-04-04
In-progress (roof level)
Nil
sur1.eew-mn
24.500295513513425,94.07564229011075
24.5942081,94.0345825
11.237577747478
Approved
2018-04-10 11:05:36
ce.eew-mn
0
Construction for the building upto roof level. (Front view)

Foundation & Inauguration
-
-
-

-
-
-