| 19321 | NEC1 | Integrated approach for enhancing ecosystem services of Nungkot Sarbei Machengpat at Andro, Imphal East, Manipur | Environment and CC | Imphal-East | Phase3 | Ongoing | 09/12/2020 |
| 19322 | DC/DRDA/IE/10/Urup | Construction Girls Hostel at Urup High School. | MOBC | Imphal-East | Phase-Ii | Ongoing | 09/12/2020 |
| 19323 | CSC BPR Keibul | Construction of Community Sanitary complex at Keibul Lamjao Gate | PHED | Bishnupur | I | completed | 08/12/2020 |
| 19324 | CSCBPR Wapokpi | Construction of CSC at Wapokpi | PHED | Bishnupur | 1 | Completed | 08/12/2020 |
| 19325 | CSCBPR Sandhong | Construction of CSC at Sandhong | PHED | Bishnupur | 1 | Completed | 08/12/2020 |
| 19326 | CSCBPR Phougakchao Ikhai | Construction of CSC at Phougakchao Ikhai | PHED | Bishnupur | 1 | Completed | 08/12/2020 |
| 19327 | CSCBPR Chairel Mangjing | Construction of CSC at Chairel Mangjing | PHED | Bishnupur | 1 | Completed | 08/12/2020 |
| 19328 | CSCBPR Nungoo Pombikhok | Construction of CSC at Nungoo Pombikhok | PHED | Bishnupur | 1 | Completed | 08/12/2020 |
| 19329 | CSCBPR Sagolpat | Construction of CSC at Sagolpat | PHED | Bishnupur | 1 | Completed | 08/12/2020 |
| 19330 | CSC BPR Wangoo Laikhong | Construction of CSC at Wangoo Laikhong | PHED | Bishnupur | 1 | Completed | 08/12/2020 |
| 19331 | CSC BPR Khordak | Construction of Community Sanitary complex at Khordak | PHED | Bishnupur | I | completed | 08/12/2020 |
| 19332 | CSC BPR Nongmaikhong | Construction of Community Sanitary complex at Nongmaikhong | PHED | Bishnupur | I | Completed | 08/12/2020 |
| 19333 | CSC BPR Moirang Khunou | Construction of Community Sanitary complex at Moirang Khunou | PHED | Bishnupur | I | Completed | 08/12/2020 |
| 19334 | CSC BPR Thangalawai | Construction of Community Sanitary complex at Thangalawai | PHED | Bishnupur | I | Completed | 08/12/2020 |
| 19335 | MSPDCL-R&E-I-053 | Erection, Installation & Commissioning of L.T. Lines at Kakching Sub-Division of Kakching Division under Non-Project Area. | POWER (MSPDCL) | Kakching | Complete | Completed | 08/12/2020 |
| 19336 | MSPDCL-R&E-I-053 | Erection, Installation & Commissioning of L.T. Lines at Kakching Sub-Division of Kakching Division under Non-Project Area. | POWER (MSPDCL) | Kakching | Complete | Completed | 08/12/2020 |
| 19337 | MSPDCL-R&E-I-053 | Erection, Installation & Commissioning of L.T. Lines at Kakching Sub-Division of Kakching Division under Non-Project Area. | POWER (MSPDCL) | Kakching | Complete | Completed | 08/12/2020 |
| 19338 | MSPDCL-R&E-I-053 | Erection, Installation & Commissioning of L.T. Lines at Kakching Sub-Division of Kakching Division under Non-Project Area. | POWER (MSPDCL) | Kakching | Complete | Completed | 08/12/2020 |
| 19339 | MSPDCL-R&E-I-053 | Erection, Installation & Commissioning of L.T. Lines at Kakching Sub-Division of Kakching Division under Non-Project Area. | POWER (MSPDCL) | Kakching | Complete | Completed | 08/12/2020 |
| 19340 | MSPDCL-R&E-I-053 | Erection, Installation & Commissioning of L.T. Lines at Kakching Sub-Division of Kakching Division under Non-Project Area. | POWER (MSPDCL) | Kakching | Complete | Completed | 08/12/2020 |