16581 | SIDF Kasom Khullen | Aug. of w/s scheme at Kasom Khullen Sub-Divisional hd qtr | PHED | Kamjong | 2 | Completed | 25/02/2021 |
16582 | SIDF Kasom Khullen | Aug. of w/s scheme at Kasom Khullen Sub-Divisional hd qtr | PHED | Kamjong | 2 | Completed | 25/02/2021 |
16583 | SIDF Kasom Khullen | Aug. of w/s scheme at Kasom Khullen Sub-Divisional hd qtr | PHED | Kamjong | 1 | Completion status | 25/02/2021 |
16584 | SIDF Kasom Khullen | Aug. of w/s scheme at Kasom Khullen Sub-Divisional hd qtr | PHED | Kamjong | 1 | Completion status | 25/02/2021 |
16585 | SIDF Kasom Khullen | Aug. of w/s scheme at Kasom Khullen Sub-Divisional hd qtr | PHED | Kamjong | 1 | Completion status | 25/02/2021 |
16586 | TML- NLCPR | Water supply scheme by water conservation at Tamenglong HQ | PHED | Tamenglong | 1 | Work in good progress | 24/02/2021 |
16587 | TML- NLCPR | Water supply scheme by water conservation at Tamenglong HQ | PHED | Tamenglong | 1 | Duithanlong dam | 24/02/2021 |
16588 | TML- NLCPR | Water supply scheme by water conservation at Tamenglong HQ | PHED | Tamenglong | 1 | Work in good progress | 24/02/2021 |
16589 | TML- NLCPR | Water supply scheme by water conservation at Tamenglong HQ | PHED | Tamenglong | 1 | Work in good progress | 24/02/2021 |
16590 | TML- NLCPR | Water supply scheme by water conservation at Tamenglong HQ | PHED | Tamenglong | 1 | Work in good progress | 24/02/2021 |
16591 | TML- NLCPR | Water supply scheme by water conservation at Tamenglong HQ | PHED | Tamenglong | 1 | Work in good progress | 24/02/2021 |
16592 | TML- NLCPR | Water supply scheme by water conservation at Tamenglong HQ | PHED | Tamenglong | 1 | Work in good progress | 24/02/2021 |
16593 | TML- NLCPR | Water supply scheme by water conservation at Tamenglong HQ | PHED | Tamenglong | 1 | Work in good progress | 24/02/2021 |
16594 | TML- NLCPR | Water supply scheme by water conservation at Tamenglong HQ | PHED | Tamenglong | 1 | Work in good progress | 24/02/2021 |
16595 | TML- NLCPR | Water supply scheme by water conservation at Tamenglong HQ | PHED | Tamenglong | 1 | Work in good progress | 24/02/2021 |
16596 | TML- NLCPR | Water supply scheme by water conservation at Tamenglong HQ | PHED | Tamenglong | 1 | Work in good progress | 24/02/2021 |
16597 | TML- NLCPR | Water supply scheme by water conservation at Tamenglong HQ | PHED | Tamenglong | 1 | Work in good progress | 24/02/2021 |
16598 | TML- NLCPR | Water supply scheme by water conservation at Tamenglong HQ | PHED | Tamenglong | 1 | Work in good progress | 24/02/2021 |
16599 | MSPCLC39 | Installation of 2x5 MVA, 33/11 kV SS along with associated 33 kV line & related civil works at Chingai, Ukhrul District on turn key basis | POWER (MSPCL) | Ukhrul | 1 | 40% | 24/02/2021 |
16600 | WRD-FCW-149 | Construction of side drain for Salam portion along Kiran Dukan, Imphal West, Manipur | Water Resources Department (WRD) | Imphal-West | 01 | Completed | 24/02/2021 |