Project Updates
Showing 15,941-15,960 of 90,974 items.
#Project CodeProject NameDepartmentDistrictPhaseProgress StatusApprove Date
     
15941SPT/Ihilo - Khipo/63Construction of IVR from Ihilo to Khipo at Makhan 4 kmPWDSenapati111%19/03/2021
15942SPT/Ihilo - Khipo/63Construction of IVR from Ihilo to Khipo at Makhan 4 kmPWDSenapati111%19/03/2021
15943ENGG/ZON(NE)/Sawombung/ImphalEast/2015Construction of 10,000 MT Capacity Food grain Godwon including ancillary structures and boundary wall at Imphal East (Sawombung)PWDImphal-EastFinalCompleted19/03/2021
15944ENGG/ZON(NE)/Sawombung/ImphalEast/2015Construction of 10,000 MT Capacity Food grain Godwon including ancillary structures and boundary wall at Imphal East (Sawombung)PWDImphal-EastFinalCompleted19/03/2021
15945ENGG/ZON(NE)/Sawombung/ImphalEast/2015Construction of 10,000 MT Capacity Food grain Godwon including ancillary structures and boundary wall at Imphal East (Sawombung)PWDImphal-EastFinalCompleted19/03/2021
15946ENGG/ZON(NE)/Sawombung/ImphalEast/2015Construction of 10,000 MT Capacity Food grain Godwon including ancillary structures and boundary wall at Imphal East (Sawombung)PWDImphal-EastFinalCompleted19/03/2021
15947Repair/NH102/320/2020-21Repairs of NH102- Clearance of chocked side drain and culverts, providing chequred tiles , reconstruction of drain walls, cover slab km 320.320-321.20PWDImphal-WestCompletedCompleted19/03/2021
15948Repair/NH102/320/2020-21Repairs of NH102- Clearance of chocked side drain and culverts, providing chequred tiles , reconstruction of drain walls, cover slab km 320.320-321.20PWDImphal-WestCompletedCompleted19/03/2021
15949Repair/NH102/320/2020-21Repairs of NH102- Clearance of chocked side drain and culverts, providing chequred tiles , reconstruction of drain walls, cover slab km 320.320-321.20PWDImphal-WestCompletedCompleted19/03/2021
15950Repair/NH102/330/2020-21Repairs to NH 102 Imphal-Moreh section ( SH: Mending of pot holes in between km 324-330)PWDImphal-WestCompletedCompleted19/03/2021
15951Repair/NH102/330/2020-21Repairs to NH 102 Imphal-Moreh section ( SH: Mending of pot holes in between km 324-330)PWDImphal-WestCompletedCompleted19/03/2021
15952EE/ED-II/Mesh Hall-IIIT/71Maint. of IEI & replacement of existing ordinary fitting by LED bubl, tube in the Mesh Hall, Boys Hostel No. 1&2 for IIIT at Mantripukhri.PWDImphal-EastIcompleted18/03/2021
15953EE/ED-II/Mesh Hall-IIIT/71Maint. of IEI & replacement of existing ordinary fitting by LED bubl, tube in the Mesh Hall, Boys Hostel No. 1&2 for IIIT at Mantripukhri.PWDImphal-EastIcompleted18/03/2021
15954EE/ED-II/Mesh Hall-IIIT/71Maint. of IEI & replacement of existing ordinary fitting by LED bubl, tube in the Mesh Hall, Boys Hostel No. 1&2 for IIIT at Mantripukhri.PWDImphal-EastIcompleted18/03/2021
15955EE/ED-II/Mesh Hall-IIIT/71Maint. of IEI & replacement of existing ordinary fitting by LED bubl, tube in the Mesh Hall, Boys Hostel No. 1&2 for IIIT at Mantripukhri.PWDImphal-EastIcompleted18/03/2021
15956EE/ED-II/Mesh Hall-IIIT/71Maint. of IEI & replacement of existing ordinary fitting by LED bubl, tube in the Mesh Hall, Boys Hostel No. 1&2 for IIIT at Mantripukhri.PWDImphal-EastIcompleted18/03/2021
15957EE/ED-II/Mesh Hall-IIIT/71Maint. of IEI & replacement of existing ordinary fitting by LED bubl, tube in the Mesh Hall, Boys Hostel No. 1&2 for IIIT at Mantripukhri.PWDImphal-EastIcompleted18/03/2021
15958EE/ED-II/Bl.-B-IIIT/70Maint. of IEI & replacement of existing ordinary fitting by LED bulb, tube in Prof. faculty bl. B at IIIT, Mantripukhri.PWDImphal-EastICompleted18/03/2021
15959EE/ED-II/Bl.-B-IIIT/70Maint. of IEI & replacement of existing ordinary fitting by LED bulb, tube in Prof. faculty bl. B at IIIT, Mantripukhri.PWDImphal-EastICompleted18/03/2021
15960EE/ED-II/Bl.-B-IIIT/70Maint. of IEI & replacement of existing ordinary fitting by LED bulb, tube in Prof. faculty bl. B at IIIT, Mantripukhri.PWDImphal-EastICompleted18/03/2021