Project Updates
Showing 1,261-1,280 of 82,519 items.
#Project CodeProject NameDepartmentDistrictPhaseProgress StatusApprove Date
     
1261RMSA/23-DI/SekmaiKhumbi12Room(Part-II)/TBlConstruction of 12 (twelve) Rooms for Higher Sec. (Science) Upgradation during 2020-21 at Sekmai Khumbi High School, Thoubal District.Education (S)Thoubalnilcompleted14/08/2024
1262SS/22-DI/khumbiHighSchool/TBLConstruction of 12 (twelve) Rooms for Higher Sec. (Science) upgradation during 2020-21 at Sekmai Khumbi High School, Thoubal District.Education (S)Thoubalnillcompleted 14/08/2024
1263SS/22-DI/khumbiHighSchool/TBLConstruction of 12 (twelve) Rooms for Higher Sec. (Science) upgradation during 2020-21 at Sekmai Khumbi High School, Thoubal District.Education (S)Thoubalnillcompleted 14/08/2024
1264IED/Bamon Kampu road/879Impvt. of Bamon Kampu road near Irilbung Police Station along Iril riverPWDImphal-East---In progress14/08/2024
1265CB@SENAPATIConstruction of District Court Building at SenapatiLaw & Legislative Affairs DepartmentSenapati155%14/08/2024
1266CB@NONEY2021Construction of District Court Building at NoneyLaw & Legislative Affairs DepartmentNoneyPhase- 153% completed14/08/2024
1267CB@KAK2021Construction of District Court Building at KakchingLaw & Legislative Affairs DepartmentKakchingPhase 190% Completed14/08/2024
1268EE/HS/Impvt Hiyangthng Lairembi templeImprovement of Hiyangthang Lairembi temple connecting road and approach roadPWDImphal-West1completed14/08/2024
1269IED/Bamon Kampu Okram-Huirom leirak/881Impvt. of Bamon Kampu Okram leirak to Huirom Leirak(Mayai lambi)PWDImphal-East---In progress14/08/2024
1270CB@KAK2021Construction of District Court Building at KakchingLaw & Legislative Affairs DepartmentKakching145%12/08/2024
1271CB@KAK2021Construction of District Court Building at KakchingLaw & Legislative Affairs DepartmentKakchingPhase 190% Completed12/08/2024
1272CB@KAK2021Construction of District Court Building at KakchingLaw & Legislative Affairs DepartmentKakchingPhase 190% Completed12/08/2024
1273CB@KAK2021Construction of District Court Building at KakchingLaw & Legislative Affairs DepartmentKakchingPhase 190% Completed12/08/2024
1274CB@KAK2021Construction of District Court Building at KakchingLaw & Legislative Affairs DepartmentKakchingPhase 190% Completed12/08/2024
1275CB@KAK2021Construction of District Court Building at KakchingLaw & Legislative Affairs DepartmentKakchingPhase 190% Completed12/08/2024
1276SHD/Longa Koireng to Thanlon Kangpokpi/216impvt of Longa Koireng to Thanlon (2km), Kangpokpi DistrictPWDKangpokpi2023-24Completed 12/08/2024
1277SHD/Longa Koireng to Thanlon Kangpokpi/216impvt of Longa Koireng to Thanlon (2km), Kangpokpi DistrictPWDKangpokpi2023-24Completed 12/08/2024
1278SHD/Longa Koireng to Thanlon Kangpokpi/216impvt of Longa Koireng to Thanlon (2km), Kangpokpi DistrictPWDKangpokpi2023-24Completed 12/08/2024
1279SHD/Longa Koireng to Thanlon Kangpokpi/216impvt of Longa Koireng to Thanlon (2km), Kangpokpi DistrictPWDKangpokpi2023-24Completed 12/08/2024
1280NNY/Thangal High School to farmland/168Impvt of road from Thangal High School to farmland via Baptist colonyPWDNoneyphase-I work in progress 12/08/2024