#Project CodeProject NameDepartmentDistrictPhaseProgress StatusApprove Date
     
11341EE/ED-1/DMC-5/2022Constn. Of Extension room of Prof. Qtr. No. 5(A& B) at DMC Campus. (S.H.-Providing of IEI in the extension room of Professor Quarter / No. 5(A&B) at DPWDImphal-WestIComplete22/09/2022
11342EE/ED-1/DMC-5/2022Constn. Of Extension room of Prof. Qtr. No. 5(A& B) at DMC Campus. (S.H.-Providing of IEI in the extension room of Professor Quarter / No. 5(A&B) at DPWDImphal-WestIComplete22/09/2022
11343EE/ED-1/DMC-5/2022Constn. Of Extension room of Prof. Qtr. No. 5(A& B) at DMC Campus. (S.H.-Providing of IEI in the extension room of Professor Quarter / No. 5(A&B) at DPWDImphal-WestIComplete22/09/2022
11344EE/ED-1/DMC-5/2022Constn. Of Extension room of Prof. Qtr. No. 5(A& B) at DMC Campus. (S.H.-Providing of IEI in the extension room of Professor Quarter / No. 5(A&B) at DPWDImphal-WestIComplete22/09/2022
11345EE/ED-1/DMC-5/2022Constn. Of Extension room of Prof. Qtr. No. 5(A& B) at DMC Campus. (S.H.-Providing of IEI in the extension room of Professor Quarter / No. 5(A&B) at DPWDImphal-WestIComplete22/09/2022
11346EE/ED-1/DMC-5/2022Constn. Of Extension room of Prof. Qtr. No. 5(A& B) at DMC Campus. (S.H.-Providing of IEI in the extension room of Professor Quarter / No. 5(A&B) at DPWDImphal-WestIComplete22/09/2022
11347EE/ED-II/Infra.-Tengnoupal/41Infra. Dev. of Tengnoupal - Constn of DC & SP Off at Teng. Dist. i/c Constn of Staff Off. for DC, sec. bark for DC's Bung., Staff Qtr. (SH-IEI Works)PWDTengnoupal1Completed22/09/2022
11348EE/ED-II/Infra.-Tengnoupal/41Infra. Dev. of Tengnoupal - Constn of DC & SP Off at Teng. Dist. i/c Constn of Staff Off. for DC, sec. bark for DC's Bung., Staff Qtr. (SH-IEI Works)PWDTengnoupal1Completed22/09/2022
11349EE/ED-II/Infra.-Tengnoupal/41Infra. Dev. of Tengnoupal - Constn of DC & SP Off at Teng. Dist. i/c Constn of Staff Off. for DC, sec. bark for DC's Bung., Staff Qtr. (SH-IEI Works)PWDTengnoupal1Completed22/09/2022
11350EE/ED-II/Infra.-Tengnoupal/41Infra. Dev. of Tengnoupal - Constn of DC & SP Off at Teng. Dist. i/c Constn of Staff Off. for DC, sec. bark for DC's Bung., Staff Qtr. (SH-IEI Works)PWDTengnoupal1Completed22/09/2022
11351Noney/2022/slab culvert-SDO Office @ 0.50km/1Reconstruction of 1m span RCC Slab culvert i/c side drain & R/Wall along the road Nungba Bazaar to SDO Office at 0.50 KmPWDNoneyFirst & Final phase100%22/09/2022
11352Noney/2022/Nungnang II to Nungnang I Road/2Impvt. of road from Nungnang II to Nungnang I (7km)PWDNoneyPhase-IWork in progress22/09/2022
11353Noney/2022/Nungnang II to Nungnang I Road/2Impvt. of road from Nungnang II to Nungnang I (7km)PWDNoneyPhase-IWork in progress22/09/2022
11354Noney/2022/Nungnang II to Nungnang I Road/2Impvt. of road from Nungnang II to Nungnang I (7km)PWDNoneyPhase-IWork in progress22/09/2022
11355Noney/2022/Nungnang II to Nungnang I Road/2Impvt. of road from Nungnang II to Nungnang I (7km)PWDNoneyPhase-IWork in progress22/09/2022
11356Noney/2022/Nungnang II to Nungnang I Road/2Impvt. of road from Nungnang II to Nungnang I (7km)PWDNoneyPhase-IWork in progress22/09/2022
11357Noney/2022/Nungnang II to Nungnang I Road/2Impvt. of road from Nungnang II to Nungnang I (7km)PWDNoneyPhase-IWork in progress22/09/2022
11358Noney/2022/Nungnang II to Nungnang I Road/2Impvt. of road from Nungnang II to Nungnang I (7km)PWDNoneyPhase-IWork in progress22/09/2022
11359CPS/18-OinamHHS-SENStrengthening of Oinam Hill High School, Senapati District.Education (S)SenapatiNilCompleted22/09/2022