87841 | CCP/Kolhen-Kamkeilon/81 | Constn. of a New Motorable road from Kolhen to Komkeilon village - 12 km i/c two slab culverts | PWD | Churachandpur | 2018-19 | completed | |
87842 | CCP/Kolhen-Kamkeilon/81 | Constn. of a New Motorable road from Kolhen to Komkeilon village - 12 km i/c two slab culverts | PWD | Churachandpur | 2018-19 | completed | |
87843 | CCP/Kolhen-Kamkeilon/81 | Constn. of a New Motorable road from Kolhen to Komkeilon village - 12 km i/c two slab culverts | PWD | Churachandpur | 2018-19 | completed | |
87844 | IED/FCI Godown-Sawombung/250 | Constn. of approach road for FCI Godown at Sawombung | PWD | Imphal-East | 1st | Ongoing | |
87845 | Ramrei-NEC | Composite water supply scheme at Ramrei and its surrounding areas | PHED | Imphal-East | 2 | 2 | |
87846 | Ramrei-NEC | Composite water supply scheme at Ramrei and its surrounding areas | PHED | Imphal-East | 2 | 2 | |
87847 | EE /BPR/Impvt. of Sandangkhong Litan /65 | Impvt. of sandangkhong Litan Makhong to L. Ibocha i/c constn. of 1.50 m slab culvert at Sandangkhong Kha | PWD | Bishnupur | Phase1 | In progress | |
87848 | EE /BPR/Impvt. of Sandangkhong Litan /65 | Impvt. of sandangkhong Litan Makhong to L. Ibocha i/c constn. of 1.50 m slab culvert at Sandangkhong Kha | PWD | Bishnupur | Phase1 | In progress | |
87849 | EE /BPR/Impvt. of Kumbi saiton - Hayaikol/66 | Impvt. of IVR connecting Kumbi saiton road from Hayaikol mayai Lambi to H. Ibungo Mapa | PWD | Bishnupur | Phase 1 | In progress | |
87850 | IED/Yumnam Khunou/360 | M/o river at Yumnam Khunou Awang Leikai - 2.0 Km | PWD | Imphal-East | 1 | State work | |
87851 | IED/Yumnam Khunou/360 | M/o river at Yumnam Khunou Awang Leikai - 2.0 Km | PWD | Imphal-East | 1 | State work | |
87852 | MSPCLC5 | Installation of 2x5 MVA, 33/11 kV Sub-Station with associated 33 kV line at Nungbi Khullen | POWER (MSPCL) | Ukhrul | G | 100 | |
87853 | MSPCLC5 | Installation of 2x5 MVA, 33/11 kV Sub-Station with associated 33 kV line at Nungbi Khullen | POWER (MSPCL) | Ukhrul | G | 100 | |
87854 | MSPCLC5 | Installation of 2x5 MVA, 33/11 kV Sub-Station with associated 33 kV line at Nungbi Khullen | POWER (MSPCL) | Ukhrul | G | 100 | |
87855 | BITE-SCERT-TBL-HEI | Construction of Block Institute of Teacher Education at Heirok Thoubal District. | Education (S) | Thoubal | Nill | Completed | |
87856 | BITE-SCERT-TBL-HEI | Construction of Block Institute of Teacher Education at Heirok Thoubal District. | Education (S) | Thoubal | Nill | Completed | |
87857 | BITE-SCERT-TBL-HEI | Construction of Block Institute of Teacher Education at Heirok Thoubal District. | Education (S) | Thoubal | Nill | Completed | |
87858 | BITE-SCERT-TBL-HEI | Construction of Block Institute of Teacher Education at Heirok Thoubal District. | Education (S) | Thoubal | Nill | Completed | |
87859 | BITE-SCERT-TBL-HEI | Construction of Block Institute of Teacher Education at Heirok Thoubal District. | Education (S) | Thoubal | Nill | Completed | |
87860 | BITE-SCERT-TBL-HEI | Construction of Block Institute of Teacher Education at Heirok Thoubal District. | Education (S) | Thoubal | nill | completed | |