Project Updates
Showing 6,861-6,880 of 31,615 items.
#Project CodeProject NameDepartmentDistrictPhaseProgress StatusApprove Date
     
6861KMJ/Kamnong to Pishing GSB/172Impvt of road from Kamnong to Pishing GSBPWDKamjong1In-progress 25/07/2024
6862KMJ/Kamnong to Pishing GSB/172Impvt of road from Kamnong to Pishing GSBPWDKamjong1in progress 25/07/2024
6863KMJ/Kamnong to Pishing GSB/172Impvt of road from Kamnong to Pishing GSBPWDKamjong1in progress 25/07/2024
6864KMJ/Kamnong to Pishing GSB/172Impvt of road from Kamnong to Pishing GSBPWDKamjong1In-progress 25/07/2024
6865KMJ/Kamnong to Pishing EW drain culvert/171Impvt of road from Kamnong to PishingPWDKamjong1In-progress 25/07/2024
6866KMJ/Kamnong to Pishing EW drain culvert/171Impvt of road from Kamnong to PishingPWDKamjong1In-progress 25/07/2024
6867KMJ/Kamnong to Pishing EW drain culvert/171Impvt of road from Kamnong to PishingPWDKamjong1In-progress 25/07/2024
6868KMJ/Kamnong to Pishing EW drain culvert/171Impvt of road from Kamnong to PishingPWDKamjong1In-progress 25/07/2024
6869KMJ/Kamnong to Pishing EW drain culvert/171Impvt of road from Kamnong to PishingPWDKamjong1In-progress 25/07/2024
6870KMJ/Kamnong to Pishing EW drain culvert/171Impvt of road from Kamnong to PishingPWDKamjong1In-progress 25/07/2024
6871KMJ/Kamnong to Pishing EW drain culvert/171Impvt of road from Kamnong to PishingPWDKamjong1In-progress 25/07/2024
6872KMJ/Kamnong to Pishing EW drain culvert/171Impvt of road from Kamnong to PishingPWDKamjong1In-progress 25/07/2024
6873SFM/22/D-I/LangjingHS/IWImplementation of School Fagathansi Mission-2nd Phase at Maklang High School, Langjing HSEducation (S)Imphal-Westnilcompleted25/07/2024
6874SFM/22/D-I/LangjingHS/IWImplementation of School Fagathansi Mission-2nd Phase at Maklang High School, Langjing HSEducation (S)Imphal-Westnilcompleted25/07/2024
6875SS/D-IV/ARAPTI/PSConstruction of Dilapidated Building Primary School under Samagra Shiksha for the Year 2023-2024 at Arapti Primary School, Imphal East.Manipur Education (S)Thoubal20223-2024complete up to roof beam25/07/2024
6876SPT/Tinsong/2021/2/5054/19-20Construction of road from Tinsong Khunou to Maichon Broder Bridge Part-II( 3 to 6 km)PWDSenapatiPhase 1In progress24/07/2024
6877SPT/Tinsong/2021/2/5054/19-20Construction of road from Tinsong Khunou to Maichon Broder Bridge Part-II( 3 to 6 km)PWDSenapati1completed24/07/2024
6878IED/Matai-Kameng/875Improvement of road Matai to Kameng 5 KmPWDImphal-Eastfinal phasework completed24/07/2024
6879IED/Potsangbam Garden-Terakhong/876Improvement of road from Potsangbam Garden to Terakhong villagePWDImphal-East---ongoing work24/07/2024
6880SCERT/D-2-SpecialCell- IWConstruction of Special Cell Science, Methematics, Social Studies, Education Technology/ Computer and Language Cell at Directorate of SCERT, LamphelpaEducation (S)Imphal-WestNILCompleted24/07/2024