Project Updates
Showing 6,241-6,260 of 31,643 items.
#Project CodeProject NameDepartmentDistrictPhaseProgress StatusApprove Date
     
6241SS/23-D3/LangthabalNMJHS(Dila)-IWConstruction of Dilapidated Building Upper Primary School under Samagra Shiksha (Elementary), Manipur during 2022-2023 at Langthabal Nambul Mapal JuniEducation (S)Imphal-West1stin progress17/09/2024
6242ND/Bldg/Infra/7Infrastructure Development of Noney.PWDNoney2nd phase60%17/09/2024
6243ND/Bldg/Infra/7Infrastructure Development of Noney.PWDNoneyFinal Phase60%17/09/2024
6244ND/Bldg/Infra/7Infrastructure Development of Noney.PWDNoneyFinal Phase60%17/09/2024
6245ND/Bldg/Infra/7Infrastructure Development of Noney.PWDNoneyFinal Phase60%17/09/2024
6246ND/Bldg/Infra/7Infrastructure Development of Noney.PWDNoneyFinal Phase60%17/09/2024
6247SHD/Impvt of Kangpokpi-Tamei Road 0-70.25/225Impvt of Kangpokpi-Tamei road 0-70.25kmPWDKangpokpiphase-I 100% works completed 17/09/2024
6248EE/BPR/M/O Nachou PanthongM/O Nachou Panthong Brick field IVR-1.95kmPWDBishnupurphase 1ongoing17/09/2024
6249SS/D-IV/UTLOU/UHSSConstruction of Upgraded Higher Secondary School at Utlou High School,Bishnupur ,Manipur 1 sh ).Construction of 19 rooms for Science & Com.Education (S)Bishnupur2023-2024The work has been complete upto Slab17/09/2024
6250SS/D-IV/UTLOU/UHSSConstruction of Upgraded Higher Secondary School at Utlou High School,Bishnupur ,Manipur 1 sh ).Construction of 19 rooms for Science & Com.Education (S)Bishnupur2023-2024The work has been complete upto Slab17/09/2024
6251SS/D-IV/UTLOU/UHSSConstruction of Upgraded Higher Secondary School at Utlou High School,Bishnupur ,Manipur 1 sh ).Construction of 19 rooms for Science & Com.Education (S)Bishnupur2023-2024The work has been complete upto Slab17/09/2024
6252SS/D-IV/UTLOU/UHSSConstruction of Upgraded Higher Secondary School at Utlou High School,Bishnupur ,Manipur 1 sh ).Construction of 19 rooms for Science & Com.Education (S)Bishnupur2023-2024The work has been complete upto Slab17/09/2024
6253SS/D-IV/UTLOU/UHSSConstruction of Upgraded Higher Secondary School at Utlou High School,Bishnupur ,Manipur 1 sh ).Construction of 19 rooms for Science & Com.Education (S)Bishnupur2023-2024The work has been complete upto Slab 17/09/2024
6254EE/ED-III/Bishnupur/IEI/CIRCUITHOUSERenovation of IEI in the Circuit House at Bishnupur.PWDBishnupur2completed 13/09/2024
6255EE/ED-III/Bishnupur/IEI/CIRCUITHOUSERenovation of IEI in the Circuit House at Bishnupur.PWDBishnupur2Completed 13/09/2024
6256EE/ED-III/Bishnupur/IEI/CIRCUITHOUSERenovation of IEI in the Circuit House at Bishnupur.PWDBishnupur2completed 13/09/2024
6257EE/ED-III/Bishnupur/IEI/CIRCUITHOUSERenovation of IEI in the Circuit House at Bishnupur.PWDBishnupur2completed 13/09/2024
6258EE/ED-III/Bishnupur/IEI/CIRCUITHOUSERenovation of IEI in the Circuit House at Bishnupur.PWDBishnupur2completed 13/09/2024
6259EE/ED-III/Bishnupur/IEI/CIRCUITHOUSERenovation of IEI in the Circuit House at Bishnupur.PWDBishnupur2completed 13/09/2024
6260EE/ED-III/Bishnupur/IEI/CIRCUITHOUSERenovation of IEI in the Circuit House at Bishnupur.PWDBishnupur2completed 13/09/2024