61901 | EE/ED-1/Alarm/CMO-Complex/2023 | Installation of Panic/Burglar alarm System at Tower no.01(Vip Gate)/02/03(Exit Gate)/04/05/06(Main Gate),Tower near cook room and CISF Barrack of CMO | PWD | Imphal-West | Phase-1 | Completed | |
61902 | EE/ED-1/Alarm/CMO-Complex/2023 | Installation of Panic/Burglar alarm System at Tower no.01(Vip Gate)/02/03(Exit Gate)/04/05/06(Main Gate),Tower near cook room and CISF Barrack of CMO | PWD | Imphal-West | Phase-1 | Completed | |
61903 | EE/ED-1/Alarm/CMO-Complex/2023 | Installation of Panic/Burglar alarm System at Tower no.01(Vip Gate)/02/03(Exit Gate)/04/05/06(Main Gate),Tower near cook room and CISF Barrack of CMO | PWD | Imphal-West | Phase-1 | Completed | |
61904 | EE/ED-1/Alarm/CMO-Complex/2023 | Installation of Panic/Burglar alarm System at Tower no.01(Vip Gate)/02/03(Exit Gate)/04/05/06(Main Gate),Tower near cook room and CISF Barrack of CMO | PWD | Imphal-West | Phase-1 | Completed | |
61905 | EE/ED-1/Alarm/CMO-Complex/2023 | Installation of Panic/Burglar alarm System at Tower no.01(Vip Gate)/02/03(Exit Gate)/04/05/06(Main Gate),Tower near cook room and CISF Barrack of CMO | PWD | Imphal-West | Phase 1 | Completed | |
61906 | EE/ED-1/Alarm/CMO-Complex/2023 | Installation of Panic/Burglar alarm System at Tower no.01(Vip Gate)/02/03(Exit Gate)/04/05/06(Main Gate),Tower near cook room and CISF Barrack of CMO | PWD | Imphal-West | Phase 1 | Completed | |
61907 | EE/ED-1/Alarm/CMO-Complex/2023 | Installation of Panic/Burglar alarm System at Tower no.01(Vip Gate)/02/03(Exit Gate)/04/05/06(Main Gate),Tower near cook room and CISF Barrack of CMO | PWD | Imphal-West | Phase 1 | Completed | |
61908 | EE/ED-1/Alarm/CMO-Complex/2023 | Installation of Panic/Burglar alarm System at Tower no.01(Vip Gate)/02/03(Exit Gate)/04/05/06(Main Gate),Tower near cook room and CISF Barrack of CMO | PWD | Imphal-West | Phase 1 | Completed | |
61909 | EE/ED-1/Alarm/CMO-Complex/2023 | Installation of Panic/Burglar alarm System at Tower no.01(Vip Gate)/02/03(Exit Gate)/04/05/06(Main Gate),Tower near cook room and CISF Barrack of CMO | PWD | Imphal-West | Phase 1 | Completed | |
61910 | IFC-TMP-1 | Thoubal Multipurpose Project | Water Resources Department (WRD) | Others | 6th phase | On going | |
61911 | IFC-TMP-1 | Thoubal Multipurpose Project | Water Resources Department (WRD) | Others | 6th phase | On going | |
61912 | EE/ED-1/Alarm/CMO-Complex/2023 | Installation of Panic/Burglar alarm System at Tower no.01(Vip Gate)/02/03(Exit Gate)/04/05/06(Main Gate),Tower near cook room and CISF Barrack of CMO | PWD | Imphal-West | Phase 1 | Completed | |
61913 | EE/ED-1/Alarm/CMO-Complex/2023 | Installation of Panic/Burglar alarm System at Tower no.01(Vip Gate)/02/03(Exit Gate)/04/05/06(Main Gate),Tower near cook room and CISF Barrack of CMO | PWD | Imphal-West | Phase 1 | Completed | |
61914 | IFC-TMP-1 | Thoubal Multipurpose Project | Water Resources Department (WRD) | Others | 6th phase | On going | |
61915 | IFC-TMP-1 | Thoubal Multipurpose Project | Water Resources Department (WRD) | Others | 6th phase | On going | |
61916 | IFC-TMP-1 | Thoubal Multipurpose Project | Water Resources Department (WRD) | Others | 6th phase | On going | |
61917 | IFC-TMP-1 | Thoubal Multipurpose Project | Water Resources Department (WRD) | Others | 6th phase | On going | |
61918 | Imphal Sewrage Project, Phase-I | Imphal Sewerage Project phase-I for Imphal Town with French Assistance | PHED | Imphal-West | Phase I | Ongoing | |
61919 | EE/JBM/Impvt Kalinagar quarry RCC culvert 3m | Impvt of Kalinagar quarry road and construction of RCC culvert 3m span at Kalinagar part 1 | PWD | Jiribam | Phase I | 96% completed, work in progress | |
61920 | EE/JBM/Impvt Kalinagar quarry RCC culvert 3m | Impvt of Kalinagar quarry road and construction of RCC culvert 3m span at Kalinagar part 1 | PWD | Jiribam | Phase I | 96% completed, work in progress | |