#Project CodeProject NameDepartmentDistrictPhaseProgress StatusApprove Date
     
56641SS/19D-I/PrajaHighSchool/IWStrengthening of School under Samagra Shiksha 2019-20 at Praja High School, Imphal West District.Education (S)Imphal-WestNilIn progress
56642SS/19D-I/PrajaHighSchool/IWStrengthening of School under Samagra Shiksha 2019-20 at Praja High School, Imphal West District.Education (S)Imphal-WestNilIn progress
56643MSPCLB18Renovation & Upgradation of Grid Sub-Stations of MSPCL under PSDFPOWER (MSPCL)Imphal-EastXYZ93% complete
56644MSPCLB18Renovation & Upgradation of Grid Sub-Stations of MSPCL under PSDFPOWER (MSPCL)Imphal-EastXYZ93%
56645MSPCLB20Construction of 132 kV line Transmission line for evacuation of Power 400/132 kV SS at Thoubal to 132 kV at kakching and Chandel on the existing 132 POWER (MSPCL)ThoubalNiceCompleted
56646MSPCLB20Construction of 132 kV line Transmission line for evacuation of Power 400/132 kV SS at Thoubal to 132 kV at kakching and Chandel on the existing 132 POWER (MSPCL)ThoubalNiceCompleted
56647RR/19D-I/PrajaHighSchool/IWRepairing/Renovation of existing Class Rooms at Praja High School, Imphal West District.Education (S)Imphal-WestNilCompleted
56648MSPCLB20Construction of 132 kV line Transmission line for evacuation of Power 400/132 kV SS at Thoubal to 132 kV at kakching and Chandel on the existing 132 POWER (MSPCL)ThoubalNiceCompleted
56649MSPCLB20Construction of 132 kV line Transmission line for evacuation of Power 400/132 kV SS at Thoubal to 132 kV at kakching and Chandel on the existing 132 POWER (MSPCL)Thoubal123Completed
56650RR/19D-I/PrajaHighSchool/IWRepairing/Renovation of existing Class Rooms at Praja High School, Imphal West District.Education (S)Imphal-WestNilCompleted
56651RR/19D-I/PrajaHighSchool/IWRepairing/Renovation of existing Class Rooms at Praja High School, Imphal West District.Education (S)Imphal-WestNilCompleted
56652MSPCLB3INSTALLATION OF 2x12.5 MVA, 132/33 kV S/S AT MOREH WITH ASSOCIATED 132 kV LINE AND RELATED CIVIL WORKPOWER (MSPCL)ChandelxyzComplete
56653MSPCLC3Installation of 2x5 MVA, 33/11 kV Sub-Station Power House Site of Loktak Down Stream HEPPOWER (MSPCL)BishnupurXyz95
56654MSPCLC3Installation of 2x5 MVA, 33/11 kV Sub-Station Power House Site of Loktak Down Stream HEPPOWER (MSPCL)BishnupurXyz95
56655MSPCLC3Installation of 2x5 MVA, 33/11 kV Sub-Station Power House Site of Loktak Down Stream HEPPOWER (MSPCL)BishnupurXyz95
56656MSPCLB22Construction of 132 kV Single circuit Transmission line from kakching 132/33 kV SS to Chandel 132/33 kV SS kV on turn key basisPOWER (MSPCL)KakchingxyzComplete
56657MSPCLB3INSTALLATION OF 2x12.5 MVA, 132/33 kV S/S AT MOREH WITH ASSOCIATED 132 kV LINE AND RELATED CIVIL WORKPOWER (MSPCL)ChandelxyzComplete
56658MSPCLB3INSTALLATION OF 2x12.5 MVA, 132/33 kV S/S AT MOREH WITH ASSOCIATED 132 kV LINE AND RELATED CIVIL WORKPOWER (MSPCL)ChandelxyzComplete
56659MSPCLC3Installation of 2x5 MVA, 33/11 kV Sub-Station Power House Site of Loktak Down Stream HEPPOWER (MSPCL)BishnupurXyz98%
56660MSPCLC3Installation of 2x5 MVA, 33/11 kV Sub-Station Power House Site of Loktak Down Stream HEPPOWER (MSPCL)BishnupurXyz95