4801 | SPT/Impvt of road at Sirong/98 | Impvt of road at Sirong | PWD | Senapati | 1 | 50% completed | 23/07/2024 |
4802 | SPT/Impvt of road at Sirong/98 | Impvt of road at Sirong | PWD | Senapati | 1 | 50% completed | 23/07/2024 |
4803 | SPT/Impvt of road at Sirong/98 | Impvt of road at Sirong | PWD | Senapati | 1 | 50% completed | 23/07/2024 |
4804 | SPT/Impvt of road at Sirong/98 | Impvt of road at Sirong | PWD | Senapati | 1 | 50% completed | 23/07/2024 |
4805 | UKL/SE-IV/NH-102A to TBCA 0.5km/18 | Impvt. of road from NH 102A to TBCA 0.50 km | PWD | Ukhrul | 2023-2024 | 100% completed | 23/07/2024 |
4806 | UKL/SE-IV/NH-102A to TBCA 0.5km/18 | Impvt. of road from NH 102A to TBCA 0.50 km | PWD | Ukhrul | 2023-2024 | 100% completed | 23/07/2024 |
4807 | UKL/SE-IV/NH-102A to TBCA 0.5km/18 | Impvt. of road from NH 102A to TBCA 0.50 km | PWD | Ukhrul | 2023-2024 | 100% completed | 23/07/2024 |
4808 | UKL/SE-IV/Awontang to KasomtangviaAwuntang/17 | Impvt. of road from Awontang to Kasomtang via Awungtang 1km | PWD | Ukhrul | 2023-2024 | Completed | 23/07/2024 |
4809 | UKL/SE-IV/Awontang to KasomtangviaAwuntang/17 | Impvt. of road from Awontang to Kasomtang via Awungtang 1km | PWD | Ukhrul | 2023-2024 | Completed | 23/07/2024 |
4810 | UKL/SE-IV/Awontang to KasomtangviaAwuntang/17 | Impvt. of road from Awontang to Kasomtang via Awungtang 1km | PWD | Ukhrul | 2023-2024 | Completed | 23/07/2024 |
4811 | UKL/SE-IV/Awontang to KasomtangviaAwuntang/17 | Impvt. of road from Awontang to Kasomtang via Awungtang 1km | PWD | Ukhrul | 2023-2024 | Completed | 23/07/2024 |
4812 | UKL/SE-IV/Impvt Awontang to Kharasom JN/5 | Impvt. of road from Awontang to Kharasom Junction via Awungtang | PWD | Ukhrul | 2023-2024 | Completed | 23/07/2024 |
4813 | UKL/SE-IV/Impvt Awontang to Kharasom JN/5 | Impvt. of road from Awontang to Kharasom Junction via Awungtang | PWD | Ukhrul | 2023-2024 | Completed | 23/07/2024 |
4814 | UKL/DAR/2022-23/Rd2/314-11 New Cannan | lmpvt. of road from New Cannan to Ngarumphung via St. Anthony's High School, Muirei. | PWD | Ukhrul | 1 | 100% completed | 23/07/2024 |
4815 | UKL/DAR/2022-23/Rd2/314-11 New Cannan | lmpvt. of road from New Cannan to Ngarumphung via St. Anthony's High School, Muirei. | PWD | Ukhrul | 1 | 100% completed | 23/07/2024 |
4816 | UKL/DAR/2022-23/Rd2/314-11 New Cannan | lmpvt. of road from New Cannan to Ngarumphung via St. Anthony's High School, Muirei. | PWD | Ukhrul | 1 | 100% completed | 23/07/2024 |
4817 | UKL/DAR/2022-23/Rd2/314-11 New Cannan | lmpvt. of road from New Cannan to Ngarumphung via St. Anthony's High School, Muirei. | PWD | Ukhrul | 1 | 100% completed | 23/07/2024 |
4818 | UKL/DAR/2022-23/Rd2/314-11 New Cannan | lmpvt. of road from New Cannan to Ngarumphung via St. Anthony's High School, Muirei. | PWD | Ukhrul | 1 | 100% completed | 23/07/2024 |
4819 | UKL/DAR/2022-23/Rd2/314-11 New Cannan | lmpvt. of road from New Cannan to Ngarumphung via St. Anthony's High School, Muirei. | PWD | Ukhrul | 1 | Completed | 23/07/2024 |
4820 | UKL/DAR/2022-23/Rd2/314-11 New Cannan | lmpvt. of road from New Cannan to Ngarumphung via St. Anthony's High School, Muirei. | PWD | Ukhrul | 1 | 100% completed | 23/07/2024 |