42481MSPCLC43Installation of 2x5 MVA 33/11 kV substation along with the associated 33 kV line and related civil works at Sanakeithel, Ukhrul District .POWER (MSPCL)Ukhrul190 percent
42482IED/Porompat road No. II/902Impvt. of Porompat road No. IIPWDImphal-East3rdcompleted
42483MSPCLC39Installation of 2x5 MVA, 33/11 kV SS along with associated 33 kV line & related civil works at Chingai, Ukhrul District on turn key basisPOWER (MSPCL)Ukhrul160
42484MSPCLC39Installation of 2x5 MVA, 33/11 kV SS along with associated 33 kV line & related civil works at Chingai, Ukhrul District on turn key basisPOWER (MSPCL)Ukhrul160
42485MSPCLC39Installation of 2x5 MVA, 33/11 kV SS along with associated 33 kV line & related civil works at Chingai, Ukhrul District on turn key basisPOWER (MSPCL)Ukhrul160
42486MSPCLC39Installation of 2x5 MVA, 33/11 kV SS along with associated 33 kV line & related civil works at Chingai, Ukhrul District on turn key basisPOWER (MSPCL)Ukhrul160
42487MSPCLC39Installation of 2x5 MVA, 33/11 kV SS along with associated 33 kV line & related civil works at Chingai, Ukhrul District on turn key basisPOWER (MSPCL)Ukhrul160
42488MSPCLC53Installation of 2x2.5 MVA, 33/11 kV sub-station along with associated 33 kV line & related civil works at Nampisha, Kamjong District on turn key basisPOWER (MSPCL)Kamjong160%
42489BRD/LEISHANG-HIDEN/2 Construction of Leishang Hiden Bridge at Pal AhanbiPWDImphal-Eastcompletedcompleted
42490BRD/LEISHANG-HIDEN/2 Construction of Leishang Hiden Bridge at Pal AhanbiPWDImphal-Eastcompleted completed
42491BRD/LEISHANG-HIDEN/2 Construction of Leishang Hiden Bridge at Pal AhanbiPWDImphal-Eastcompleted completed
42492BRD/LEISHANG-HIDEN/2 Construction of Leishang Hiden Bridge at Pal AhanbiPWDImphal-Eastcompleted completed
42493BRD/LEISHANG-HIDEN/2 Construction of Leishang Hiden Bridge at Pal AhanbiPWDImphal-Eastcompleted completed
42494WRD-WB-06Rejuvenation of Lamphelpat Waterbody(SH - Construction of bridge for motors, pedestrians etc. at Lamphelpat, Imphal West, Manipur)Water Resources Department (WRD)Imphal-WestPile Reinforcement Ongoing
42495WRD-WB-06Rejuvenation of Lamphelpat Waterbody(SH - Construction of bridge for motors, pedestrians etc. at Lamphelpat, Imphal West, Manipur)Water Resources Department (WRD)Imphal-WestFoundation workongoing
42496BRD/Bridge-Sun Light Club/24Constn. of RCC Bridge Kongba River at Sun Light Club MapaPWDImphal-Eastfinalcompleted
42497SE-I/IE/DRP/2023-24/R1/17-1-RIDF SawombungImprovement of road from Sawombung to Sagolmang Bazar via KeibiPWDImphal-Eastmid phaseongoing work
42498SE-I/IE/DRP/2023-24/R1/17-1-RIDF SawombungImprovement of road from Sawombung to Sagolmang Bazar via KeibiPWDImphal-Eastmid phaseongoing work
42499SE-I/DRP/2023-24/Rc-78 -Lei Ingkhol 1m SCConstruction of drain at Chingmeirong Lei Ingkhol including 1 m span RCC slab culvertPWDImphal-EastNA100%