3921 | SDH/DAR/2022-23/R2/328-10 Mission Road | Impvt. of Mission road to Hydro Colony, Kangpokpi via Hangmi Veng | PWD | Kangpokpi | phase-I | 100% works completed | 20/09/2024 |
3922 | SDH/DAR/2022-23/R2/328-10 Mission Road | Impvt. of Mission road to Hydro Colony, Kangpokpi via Hangmi Veng | PWD | Kangpokpi | phase-I | 100% works completed | 20/09/2024 |
3923 | Ukl/2022/Eastern-Western circular road/RIDF/1 | Impvt. of Eastern and Western circular road in Ukhrul | PWD | Ukhrul | Phase 1 | 100% | 19/09/2024 |
3924 | SHD/Thangal Surung to Khongaba Kei Dam/253 | Constn of IVR from Thangal Surung to Khongaba Kei Dam, Saikul Block-3km | PWD | Kangpokpi | 2023-24 | 70% progress | 19/09/2024 |
3925 | SHD/Thangal Surung to Khongaba Kei Dam/253 | Constn of IVR from Thangal Surung to Khongaba Kei Dam, Saikul Block-3km | PWD | Kangpokpi | 2023-24 | 70% progress | 19/09/2024 |
3926 | SHD/Thangal Surung to Khongaba Kei Dam/253 | Constn of IVR from Thangal Surung to Khongaba Kei Dam, Saikul Block-3km | PWD | Kangpokpi | 2023-24 | 70% progress | 19/09/2024 |
3927 | SHD/Thangal Surung to Khongaba Kei Dam/253 | Constn of IVR from Thangal Surung to Khongaba Kei Dam, Saikul Block-3km | PWD | Kangpokpi | 2023-24 | 70% progress | 19/09/2024 |
3928 | SHD/Thangal Surung to Khongaba Kei Dam/253 | Constn of IVR from Thangal Surung to Khongaba Kei Dam, Saikul Block-3km | PWD | Kangpokpi | 2023-24 | 70% progress | 19/09/2024 |
3929 | SHD/Thangal Surung to Khongaba Kei Dam/253 | Constn of IVR from Thangal Surung to Khongaba Kei Dam, Saikul Block-3km | PWD | Kangpokpi | 2023-24 | 70% progress | 19/09/2024 |
3930 | SHD/Thangal Surung to Khongaba Kei Dam/253 | Constn of IVR from Thangal Surung to Khongaba Kei Dam, Saikul Block-3km | PWD | Kangpokpi | 2023-24 | 70% progress | 19/09/2024 |
3931 | SHD/Thangal Surung to Khongaba Kei Dam/253 | Constn of IVR from Thangal Surung to Khongaba Kei Dam, Saikul Block-3km | PWD | Kangpokpi | 2023-24 | in progress | 19/09/2024 |
3932 | BRD/RCC Bridge-Kamong Meisnam/35 | Constn. of RCC Bridge over Leimakhong River at Kamong Meisnam Leikai | PWD | Imphal-West | --- | completed | 19/09/2024 |
3933 | TML/Noney-Marangching/6 | Impvt. of Noney-Marangching (Railway Project road) (SH: Shingling 8.20 Km WBM Gr-II 8.20 Km and constn. of 900 mm dia RCC pipe culvert NP3 7.50 Rm ... | PWD | Tamenglong | 3rd | completed | 19/09/2024 |
3934 | TML/Noney-Marangching/6 | Impvt. of Noney-Marangching (Railway Project road) (SH: Shingling 8.20 Km WBM Gr-II 8.20 Km and constn. of 900 mm dia RCC pipe culvert NP3 7.50 Rm ... | PWD | Tamenglong | 3rd | completed | 19/09/2024 |
3935 | SS/24-DI/N.TomchouHrSS/IW | Construction of Govt. Secondary & Hr. Secondary School under Samagra Shiksha for the year 2023-24 at N. Tomchou Hr. Sec. School, Imphal West | Education (S) | Imphal-West | in progress | nil | 19/09/2024 |
3936 | TML/Noney-Marangching/6 | Impvt. of Noney-Marangching (Railway Project road) (SH: Shingling 8.20 Km WBM Gr-II 8.20 Km and constn. of 900 mm dia RCC pipe culvert NP3 7.50 Rm ... | PWD | Tamenglong | 3rd | completed | 19/09/2024 |
3937 | SS/24-DI/N.TomchouHrSS/IW | Construction of Govt. Secondary & Hr. Secondary School under Samagra Shiksha for the year 2023-24 at N. Tomchou Hr. Sec. School, Imphal West | Education (S) | Imphal-West | nil | in progress | 19/09/2024 |
3938 | SS/24-DI/N.TomchouHrSS/IW | Construction of Govt. Secondary & Hr. Secondary School under Samagra Shiksha for the year 2023-24 at N. Tomchou Hr. Sec. School, Imphal West | Education (S) | Imphal-West | nil | in progress | 19/09/2024 |
3939 | SS/24-DI/N.TomchouHrSS/IW | Construction of Govt. Secondary & Hr. Secondary School under Samagra Shiksha for the year 2023-24 at N. Tomchou Hr. Sec. School, Imphal West | Education (S) | Imphal-West | nil | inprogess | 19/09/2024 |
3940 | TML/Noney-Marangching/6 | Impvt. of Noney-Marangching (Railway Project road) (SH: Shingling 8.20 Km WBM Gr-II 8.20 Km and constn. of 900 mm dia RCC pipe culvert NP3 7.50 Rm ... | PWD | Tamenglong | 3rd | completed | 19/09/2024 |