30381MSPCLB5INSTALLATION OF 2x12.5 MVA, 132/33 kV S/S ALONG WITH ASSOCIATED 132 kV LINE AND RELATED WORKS AT CHANDEL IN MANIPURPOWER (MSPCL)ChandelOk100%
30382MSPCLB5INSTALLATION OF 2x12.5 MVA, 132/33 kV S/S ALONG WITH ASSOCIATED 132 kV LINE AND RELATED WORKS AT CHANDEL IN MANIPURPOWER (MSPCL)ChandelOk100%
30383IFCD-FCW-18Anti-Erosion & Flood Control Scheme under one time assistance of Central Plan Scheme.Water Resources Department (WRD)Others1st phaseOn-going
30384NRDWP/PHUBALAAUGMENTATION OF PHUBALA WATER SUPPLY SCHEMEPHEDBishnupur2Ongoing
30385IFCD-FCW-18Anti-Erosion & Flood Control Scheme under one time assistance of Central Plan Scheme.Water Resources Department (WRD)Others1st phaseOn-going
30386IFCD-FCW-18Anti-Erosion & Flood Control Scheme under one time assistance of Central Plan Scheme.Water Resources Department (WRD)OthersPhase IOngoing work
30387IFCD-FCW-18Anti-Erosion & Flood Control Scheme under one time assistance of Central Plan Scheme.Water Resources Department (WRD)OthersPhase IOngoing work
30388IFCD-FCW-18Anti-Erosion & Flood Control Scheme under one time assistance of Central Plan Scheme.Water Resources Department (WRD)OthersPhase IOngoing work
30389IFCD-FCW-18Anti-Erosion & Flood Control Scheme under one time assistance of Central Plan Scheme.Water Resources Department (WRD)OthersPhase IOngoing work
30390IFCD-FCW-18Anti-Erosion & Flood Control Scheme under one time assistance of Central Plan Scheme.Water Resources Department (WRD)OthersPhase IOngoing work
30391IFCD-FCW-18Anti-Erosion & Flood Control Scheme under one time assistance of Central Plan Scheme.Water Resources Department (WRD)OthersPhase IOngoing work
30392EE/NNY/PHE/WORKS/2017-18/01Water Supply Scheme at Kabui KhullenPHEDNoneyPhase 1In progress
30393EE/NNY/PHE/WORKS/2017-18/01Water Supply Scheme at Kabui KhullenPHEDNoneyPhase 1In progress
30394EE/NNY/PHE/WORKS/2017-18/01Water Supply Scheme at Kabui KhullenPHEDNoneyPhase1In progress
30395IFCD-FCW-18Anti-Erosion & Flood Control Scheme under one time assistance of Central Plan Scheme.Water Resources Department (WRD)OthersFirst phaseOn going
30396IFCD-FCW-18Anti-Erosion & Flood Control Scheme under one time assistance of Central Plan Scheme.Water Resources Department (WRD)OthersFirst phaseOn going
30397IFCD-FCW-18Anti-Erosion & Flood Control Scheme under one time assistance of Central Plan Scheme.Water Resources Department (WRD)OthersFirst phaseOn going
30398IFCD-FCW-18Anti-Erosion & Flood Control Scheme under one time assistance of Central Plan Scheme.Water Resources Department (WRD)OthersFirst phaseOn going
30399IFCD-FCW-18Anti-Erosion & Flood Control Scheme under one time assistance of Central Plan Scheme.Water Resources Department (WRD)OthersFirst phaseOn going
30400IFCD-FCW-18Anti-Erosion & Flood Control Scheme under one time assistance of Central Plan Scheme.Water Resources Department (WRD)OthersFirst phaseOn going