Project Updates
Showing 3,021-3,040 of 88,235 items.
#Project CodeProject NameDepartmentDistrictPhaseProgress StatusApprove Date
     
3021UKL/SE-IV/Impvt of Kuirei Huishu IVR/48Construction/Impvt of Kuirei Huishu IVRPWDUkhrulPhase 180% progress18/09/2024
3022Ukl/SE-IV/Kuirei Hiushu IVR(Slab culverts)/22Impvt. of Kuirei Huishu IVR (Slab culvert of 1m and 1.5m span)PWDUkhrulPhase 1completed 18/09/2024
3023Ukl/SE-IV/Kuirei Hiushu IVR(Slab culverts)/22Impvt. of Kuirei Huishu IVR (Slab culvert of 1m and 1.5m span)PWDUkhrulPhase 1completed 18/09/2024
3024Ukl/SE-IV/Kuirei Hiushu IVR(Slab culverts)/22Impvt. of Kuirei Huishu IVR (Slab culvert of 1m and 1.5m span)PWDUkhrulPhase 1completed 18/09/2024
3025UKL/SE-IV/Impvt of Kuirei Huishu IVR/48Construction/Impvt of Kuirei Huishu IVRPWDUkhrulPhase 1completed 18/09/2024
3026UKL/SE-IV/Impvt of Kuirei Huishu IVR/48Construction/Impvt of Kuirei Huishu IVRPWDUkhrulPhase 1completed 18/09/2024
3027SS/24D-I/NetajiSubhashChandraBose/IEConstruction of Govt. Secondary & Hr. Secondary School under Samagra Shiksha for the year 2023-24 at Netaji Subhash Chandra Bose Awasiya Vidyalaya, ImEducation (S)Imphal-Eastnilinprogess 18/09/2024
3028SS/24D-I/NetajiSubhashChandraBose/IEConstruction of Govt. Secondary & Hr. Secondary School under Samagra Shiksha for the year 2023-24 at Netaji Subhash Chandra Bose Awasiya Vidyalaya, ImEducation (S)Imphal-Eastnilinprogess 18/09/2024
3029SS/24D-I/NetajiSubhashChandraBose/IEConstruction of Govt. Secondary & Hr. Secondary School under Samagra Shiksha for the year 2023-24 at Netaji Subhash Chandra Bose Awasiya Vidyalaya, ImEducation (S)Imphal-Eastnilinprogess 18/09/2024
3030MWSP_PHED_NDBManipur Water Supply Project (NDB)PHEDOthersPackage IXOngoing18/09/2024
3031MWSP_PHED_NDBManipur Water Supply Project (NDB)PHEDOtherspackage IXOngoing18/09/2024
3032SHD/Construction of P Khotha to K Sajal/227Construction of road from P. Khothah to K. SajalPWDKangpokpi2021 - 22 completed 17/09/2024
3033SHD/Construction of P Khotha to K Sajal/227Construction of road from P. Khothah to K. SajalPWDKangpokpiphase-I 100% works completed 17/09/2024
3034SPT/DAR/2022-23/R1/343-13 bridge at Likhruri Construction of bridge at Likhrurii Kori (rivulet) between Makhan and Chakumei.PWDSenapati150% progress17/09/2024
3035SPT/DAR/2022-23/R1/343-13 bridge at Likhruri Construction of bridge at Likhrurii Kori (rivulet) between Makhan and Chakumei.PWDSenapati150% progress17/09/2024
3036SPT/DAR/2022-23/R1/343-13 bridge at Likhruri Construction of bridge at Likhrurii Kori (rivulet) between Makhan and Chakumei.PWDSenapati150% progress17/09/2024
3037SPT/DAR/2022-23/R1/343-13 bridge at Likhruri Construction of bridge at Likhrurii Kori (rivulet) between Makhan and Chakumei.PWDSenapati150% progress17/09/2024
3038SPT/DAR/2022-23/R1/343-13 bridge at Likhruri Construction of bridge at Likhrurii Kori (rivulet) between Makhan and Chakumei.PWDSenapati150% progress17/09/2024
3039SPT/DAR/2022-23/R1/342-12 bridge over Marei KConstruction of minor bridge over Marei Kori (river) at Ralu, Makhan, SenapatiPWDSenapati1completed17/09/2024
3040SPT/DAR/2022-23/R1/342-12 bridge over Marei KConstruction of minor bridge over Marei Kori (river) at Ralu, Makhan, SenapatiPWDSenapati1completed 17/09/2024