| 20401 | IED/Naharup Thong-Makha Pat/407 | Impvt. of road from Naharup Thong to Makha Pat Eastern side - 1.5 km | PWD | Imphal-East | 1st | Ongoing | 23/11/2020 |
| 20402 | BD-III/Mechanical office | Construction of Office and Workshop building for Mechanical Division No.-I & II at Kongba Lairenpat. | PWD | Imphal-East | 1 | In Progress | 23/11/2020 |
| 20403 | BD-III/Mechanical office | Construction of Office and Workshop building for Mechanical Division No.-I & II at Kongba Lairenpat. | PWD | Imphal-East | 1 | In Progress | 23/11/2020 |
| 20404 | BD-III/Mechanical office | Construction of Office and Workshop building for Mechanical Division No.-I & II at Kongba Lairenpat. | PWD | Imphal-East | 1 | In Progress | 23/11/2020 |
| 20405 | BD-III/Mechanical office | Construction of Office and Workshop building for Mechanical Division No.-I & II at Kongba Lairenpat. | PWD | Imphal-East | 1 | In Progress | 23/11/2020 |
| 20406 | EDU010CCP | Construction of Vungzagen Higher Secondary School | MOBC | Churachandpur | 12th Plan | Ongoing | 23/11/2020 |
| 20407 | EDU010CCP | Construction of Vungzagen Higher Secondary School | MOBC | Churachandpur | 12th Plan | Ongoing | 23/11/2020 |
| 20408 | KCG/DARPAN/BLDG(P)/2020/03 | Construction of Toilet Complex in DC office and left out fencing of the DC Complex at Kakching. | PWD | Kakching | 1st | 70% | 23/11/2020 |
| 20409 | KCG/DARPAN/BLDG(P)/2020/03 | Construction of Toilet Complex in DC office and left out fencing of the DC Complex at Kakching. | PWD | Kakching | 1st | 70% | 23/11/2020 |
| 20410 | KCG/DARPAN/BLDG(P)/2020/03 | Construction of Toilet Complex in DC office and left out fencing of the DC Complex at Kakching. | PWD | Kakching | 1st | 70% | 23/11/2020 |
| 20411 | KCG/DARPAN/BLDG(P)/2020/03 | Construction of Toilet Complex in DC office and left out fencing of the DC Complex at Kakching. | PWD | Kakching | 1st | 70% | 23/11/2020 |
| 20412 | KCG/DARPAN/BLDG(P)/2020/03 | Construction of Toilet Complex in DC office and left out fencing of the DC Complex at Kakching. | PWD | Kakching | 1st | 70% | 23/11/2020 |
| 20413 | KCG/DARPAN/BLDG(P)/2020/03 | Construction of Toilet Complex in DC office and left out fencing of the DC Complex at Kakching. | PWD | Kakching | 1st | 70% | 23/11/2020 |
| 20414 | IED/Gurumayum leirak/476 | M/o road at Gurumayum leirak, Road at Akoijam Leirak, Road at ramanda leirak, Road at Koijam Nobin leirak | PWD | Imphal-East | Na | In progress | 23/11/2020 |
| 20415 | IED/Kangla Moat-Sangai 2018/474 | M/o approach road at Kangla Museum at Kangla Moat in connection with Sangai Festival 2018 | PWD | Imphal-East | Na | Completed | 23/11/2020 |
| 20416 | IED/Kangla Moat-Sangai 2018/474 | M/o approach road at Kangla Museum at Kangla Moat in connection with Sangai Festival 2018 | PWD | Imphal-East | Na | Completed | 23/11/2020 |
| 20417 | IED/Sanjenbam-Gouranagar (4-7.5 km)/254 | Impvt. of approach road from Sanjenbam to Gouanagar vice -versa Gouranagar Mahadeva Repeater Station (Baruni) from 4.00 Km to 7.50 Km | PWD | Imphal-East | 1 | In progress | 21/11/2020 |
| 20418 | IED/CD-Imphal East-II/252 | Impvt. of CD Block at Imphal East-II (SH: Block Bldg, Drainage, Toilet and Fencing repair) | PWD | Imphal-East | 1 | In progress | 21/11/2020 |
| 20419 | BD-II/AE-I/G+2 Cheirap Court uripok | M/o G+2 Court Bldg and repairing of Compound wall at Cheirap Court Complex, Uripok | PWD | Imphal-West | Phase 1 | In progress | 20/11/2020 |
| 20420 | BD-II/AE-I/G+2 Cheirap Court uripok | M/o G+2 Court Bldg and repairing of Compound wall at Cheirap Court Complex, Uripok | PWD | Imphal-West | Phase 1 | In progress | 20/11/2020 |