Showing 10,741-10,760 of 11,201 items.
#CodeNameDepartmentDistrictApproved Project Cost (in Lakhs)Fund Utilized so far(in Lakhs)Source of FundingPhysical ProgressFinancial ProgressSectorCreate DateFinancial YearProject Start DateStatus
      
 
10741IED/Thongju-Lilong/37Impvt. of Thongju Leirak to Lilong Shantipur roadPWDImphal-East33.5916.00State Plan07/11/20172016-2017-In-ProgressView
10742IED/Wangkem Lairembi-Main/36Impvt. of Wangkhem Lairembi to main road left sidePWDImphal-East15.689.00State Plan07/11/20172016-2017-In-ProgressView
10743stg16-17langjinghsstrengthening of existing high schoolEdu (S) - SSA & RMSAImphal-West51.3520.54CSS / CPS06/11/20172016-2017-In-ProgressView
10744IED/Pong road-Tinseed road/35M/o Pong road & Tinseed road i/c extension of slab culvert along the road connecting DC & Pong roadPWDImphal-East37.020State Plan04/11/20172012-2013-In-ProgressView
10745rsq13-14seroupracticalhsconstruction of staff quarter, 2013-14Edu (S) - SSA & RMSAThoubal33.9813.59CSS / CPS04/11/20172016-2017-In-ProgressView
1074610(1)SD/MQCD/TSM/Kangla/Light & Sound Show/29Design & Installation of Light & Sound Show and Construction of Gallery in front of Brindaban Chandra Temple at KanglaPWDImphal-West846.80494.51Others03/11/20172015-2016-In-ProgressView
10747ED1/Court Complex Cheirap Modern/7Modernisation of sub-main wiring & replacemt of LED fixt. in Judge chamber &Court rooms, 12 nos. i/c e-court rooms, 3 nos. at Cheirap Court Complex.PWDImphal-West200.000.00Others03/11/20172017-2018-In-ProgressView
10748ED1/Court Complex Cheirap SH-II/6Renovation of IEI in Old Court Bldg at Cheirap Court Compl. SH-I Prov. of light & plug pt. in Court room, Jugde Chamber & PA room from UPS.PWDImphal-West200.000.00Others03/11/20172017-2018-In-ProgressView
10749ED1/Court Complex Cheirap/5Renovation of IEI in Old Court Bldg at Cheirap Court Compl. Uripok SH-I Renovation of IEI in eastern Portion of Cheirap Court.PWDImphal-West200.000.00Others03/11/20172017-2018-In-ProgressView
10750ED1/Court Complex Lamphel/4Modernisation of sub-main wiring & replacemt of LED fixt. in Judge chamber &Court rooms, 12 nos. i/c e-court rooms, 3 nos. at Lamphel Court Complex.PWDImphal-West200.000.00Others03/11/20172017-2018-In-ProgressView
10751EE/ED-II/Dermatology JNIMS/16Renovation of IEI in the Office chamber of HOD (Dermatology) and HOD (T.D. & Chest) for JNIMSPWDImphal-East6.950.00Others02/11/20172017-2018-In-ProgressView
10752EE/ED-II/Family Qtr. JNIMS/15Providing yard lighting in the campus of Family Qtr. of JNIMS.PWDImphal-East6.950.00Others02/11/20172017-2018-In-ProgressView
10753HSD/Wangoi-Mutum/Thiyam-Kokchai/OinamWangoi/71. M/o of Wangoi to Mutum Phibou Rd.-4.8Km 2. Thiyam Leishangkhong to Kokchai Rd.-6.20Km, 3. Oinam Wangoi rd.-3km. 4. Nambol Hiyanthang rd. 1 KmPWDImphal-West37.710State Plan02/11/20172012-2013-In-ProgressView
107549/4/11-GAD(W)/WstrnBlck/NewSectt/SH-5thFloorConstn of 4th floor (Western Blck), New Sectt, Imphal.(SH:- Constn of part of the 5th floor (Southrn) Side of the Western block of the New SecttPWDImphal-West94.0063.00State Plan02/11/20172017-2018-In-ProgressView
10755HSD/Pucca Drain/Sati Khongang-Bengoon/6Construction of pucca drain from Sati Khongnang Leirak Machine to Bengoon Makha Paton Taba Lambi -780m.PWDImphal-West38.010State Plan02/11/20172012-2013-In-ProgressView
10756HSD/Hiyangthang-Irom Meijrao/5M/o road from Hiyangthang Makha Leikai to Irom Meijrao (SH:WBM & PC 0.60 km to 3.20 km)PWDImphal-West60.000State Plan28/10/20172012-2013-In-ProgressView
10757EE/ED-II/IIIT Manipur/14Providing IEI in the existing building for Class room Girl’s Hostel & Boy’s Hostel No.3 at IIIT temporary campus at Mantripukhri (Electrical Part)PWDImphal-East42.120.00Others26/10/20172017-2018-In-ProgressView
10758EE/ED-III/Takmu/1Development of Tourist Resort at Sendra Hillock, Water Sports complex at Takmu and other Tourist facilities in adjoining area, Bishnupur District.PWDBishnupur553.720.00Central Sector26/10/20172017-2018-In-ProgressView
10759Ukl/Guest House/Shiroi Lily/6Improvement of Guest House at Shiroi LilyPWDUkhrul140.860State Plan23/10/20172017-2018-In-ProgressView
10760Ukl/Building/Guest House/Shiroi Lily/6Improvement of Guest House at Shiroi LilyPWDUkhrul140.87110.43State Plan23/10/20172012-2013-In-ProgressView