#CodeNameDepartmentDistrictApproved Project Cost (in Lakhs)Fund Utilized so far(in Lakhs)Source of FundingCreate DateFinancial YearProject Status
   
 
4461SPT/HP-02Hand PumpMOBCSenapati5.003.80CSS / CPS19/03/20212020-2021Project Status
4462SPT/HP-01Hand PumpMOBCSenapati5.003.80CSS / CPS19/03/20212020-2021Project Status
4463MID-NESIDS(FDR)-2019-20-NamkaolongRe-construction of Pick-Up Weir across Duichunglok stream of Taroujang, Namkalong Part-II, Khoupum Valley, Noney District.Minor Irrigation DepartmentNoney46.060.00CSS / CPS18/03/20212020-2021Project Status
4464EE/ED-II/Mesh Hall-IIIT/71Maint. of IEI & replacement of existing ordinary fitting by LED bubl, tube in the Mesh Hall, Boys Hostel No. 1&2 for IIIT at Mantripukhri.PWDImphal-East15.000Others18/03/20212020-2021Project Status
4465EE/ED-II/Bl.-B-IIIT/70Maint. of IEI & replacement of existing ordinary fitting by LED bulb, tube in Prof. faculty bl. B at IIIT, Mantripukhri.PWDImphal-East12.000Others18/03/20212020-2021Project Status
4466EE/ED-II/Bl.-A-IIIT/69Maint. of IEI & replacement of existing ordinary fitting by LED bulb, tube in Diretor Off & Prof. faculty bl A, Admn office at IIIT at Mantripukhri.PWDImphal-East25.000Others18/03/20212020-2021Project Status
4467EE/ED-II/Sangai-17/68Providing lighting arrangement in the requisit stalls for the Sangai Festival, 17 at Hafta Kangjeibung, Konung Lampak, Imphal East.PWDImphal-East24.000.00Others18/03/20212020-2021Project Status
4468MO/NH102/GSB/326M/O to NH102 -Providing GSB for side berm from km 326.84- km 328PWDImphal-West9.970Others18/03/20212020-2021Project Status
4469MO/NH102/GSB/328M/O to NH-102- Providing GSB for side berm from km 328.00- km 329.950PWDImphal-West15.000.00Others18/03/20212020-2021Project Status
4470MO/NH102/GSB/328M/O to NH-102- Providing GSB for side berm from km 328.00- km 329.950PWDImphal-West15.000Others18/03/20212020-2021Project Status
4471MO/NH-150/Widening culvert/2020-21M/O- Widening of existing in pipe culvert at km 412.152, 420.560, 423.327, 424.230 and 427.200PWDBishnupur18.180Others18/03/20212020-2021Project Status
4472BD-I/TombisanaMktConstruction of Tombisana Market for rehabilitation of Women's Vendors at Khwairamband Bazar,Imphal(Balance Works).PWDImphal-West4933.651340.91Others17/03/20212020-2021Project Status
4473MO/NH-150/462.150/20-21M/O- Painting of central median ,footpath , wall of Kekrupat from km 454.798 to km 462.150PWDImphal-West9.340Others17/03/20212020-2021Project Status
4474MO/NH-150/km 462.15/2020-21M/O- Painting of central median, footpath, wall of Kekrupat from km 462.15 to km 465.200PWDImphal-West8.000Others17/03/20212020-2021Project Status
4475MO/NH-150/Rumble strip/2020-21M/O- Construction of jersey barrier and rumble strip at different junctions of NH-150 (New NH-02) PWDImphal-West15.520Others17/03/20212020-2021Project Status
4476MID-IV-PMKSY-KPI-22-2020-21-PangmolConstructionof P/W & I.C a/c Tuibong River at Pangmol Sadar HillsMinor Irrigation DepartmentKangpokpi40.000.00CSS / CPS17/03/20212020-2021Project Status
4477MID-IV-PMKSY-KPI-21-2020-21-J.ShongtunConstructionof Irrigation Tank at J.Songtun Village.Minor Irrigation DepartmentKangpokpi30.000.00CSS / CPS17/03/20212020-2021Project Status
4478MID-IV-PMKSY-KPI-15-2020-21-MITHAPANI PANJANGConst. Of P/W&I/C. a/c Mithapani stream at Panjang villageMinor Irrigation DepartmentKangpokpi50.000.00CSS / CPS17/03/20212020-2021Project Status
4479MID-IV-PMKSY-KPI-18-2020-21-G.PhaibungConstruction of Irrigation Tank at G.Phaibung Village.Minor Irrigation DepartmentKangpokpi30.000.00CSS / CPS17/03/20212020-2021Project Status
4480MO/NH-37/3.22/2020-21M/O -Reconstruction of damaged RCC drain slab cover and cleaning of clogged drain from o.56 to 3.22 km on NH-37 PWDImphal-West17.490Others17/03/20212020-2021Project Status