Project Lists

Showing 2,861-2,880 of 11,201 items.
#CodeNameDepartmentDistrictApproved Project Cost (in Lakhs)Fund Utilized so far(in Lakhs)Source of FundingPhysical ProgressFinancial ProgressSectorCreate DateFinancial YearProject Start DateStatus
      
 
2861FDR/NH-137A/2022-23/Restoration/ km 15.35FDR to NH-137A, Imphal- Kakching lamkhai section 2022-23, Restoration of damaged pavement from km 9.88- km 15.35PWDImphal-West47.310Others14/03/20232022-2023-In-ProgressView
2862Heirok Part ii Mayai Leikai PSConstruction of Additional Class Room at Heirok Part ii Mayai Leikai PS , Approved year 2018-19Edu (S) - SSA & RMSAThoubal18.603.54CSS / CPS14/03/20232022-2023-In-ProgressView
2863Haoreibi Awang Leikai Tera Makhong UPS Construction of Additional Class room approved year 2021-22Edu (S) - SSA & RMSAThoubal14.929.78CSS / CPS14/03/20232022-2023-In-ProgressView
2864JJM/ NarumWater Supply Scheme at NarumPHEDTengnoupal5200000.000.00Central Sector14/03/20232021-2022-In-ProgressView
2865JJM/ Rilram CentreWater Supply Scheme at Rilram CentrePHEDTengnoupal4200000.000.00Central Sector14/03/20232021-2022-In-ProgressView
2866SS/D-2-ShingkapHS Lab- KJGStrengthening of Government Sec. & Hr. Sec. under Samagra Shiksha Manipur 2021-22 at Shingkap High School, Kamjong, Manipur.Education (S)Kamjong31.430Others13/03/20232021-2022-In-ProgressView
2867WRD-FCW-349Channelisation of Arong River at CharangpatWater Resources Department (WRD)Thoubal25.500State Plan13/03/20232022-2023-CompletedView
2868OR/NH-02/2022-23/Clogged drain/439OR to NH-02 Churachandpur- Imphal Section, 2022-23, Cleaning of clogged drain from km 434.00- km 439.00PWDBishnupur6.180Others13/03/20232022-2023-In-ProgressView
2869OR/NH-02/2022-23/Protection Work/450.196OR to NH-02 Churachandpur- Imphal Section, 2022-23, Construction of Protection Works at km 450.196PWDImphal-West4.950Others13/03/20232022-2023-In-ProgressView
2870UKL-JJM-LeiyaramAug. of W/S Scheme at LeiyaramPHEDUkhrul85.000.00Others13/03/20232019-2020-In-ProgressView
2871OR/NH-02/2022-23/Cleaning side berm/454.798OR to Nh-02 Churachandpur- Imphal Section, 2022-23, Cleaning of side berm & removal of unserviceable soil from km 452.00 to km 454.798PWDImphal-West4.970Others13/03/20232022-2023-In-ProgressView
2872UKL/JJM/LeiyaramAug. of W/s scheme at LeiyaramPHEDUkhrul85.000Others13/03/20232019-2020-In-ProgressView
2873G-20/NH-02/Repairing/KeishampatRepairing of RCC railing post and construction of RCC slab cover at KeishampatPWDImphal-East9.020Others13/03/20232022-2023-In-ProgressView
2874M/O /NH-02/ Traffic IslandM/O to NH-02 Imphal-Yaingangpokpi section 2022-23, Construction of Traffic Island at Hodam leirak & Tiddim ground JunctionPWDImphal-West5.130Others13/03/20232022-2023-In-ProgressView
2875MO/NH-202/Clearance/488M/O to NH-202, Imphal- Yaingangpokpi section, 2022-23 , Clearance of road side berm from km 468.00 to km 488.00PWDImphal-East10.000Others13/03/20232022-2023-In-ProgressView
2876TML-PHE/OM/01PWProtection work PHEDTamenglong20.000.00State Plan12/03/20232022-2023-In-ProgressView
2877UKL/JJM/MoulsohoiAug. of W/S Scheme at MoulsohoiPHEDUkhrul82.000Others07/03/20232021-2022-In-ProgressView
2878UKL/JJM/Mollen KamseiAug. of W/S Scheme at Mollen KamseiPHEDUkhrul90.000.00Others07/03/20232021-2022-In-ProgressView
2879UKL/NDB/CHAMPHUNG W/s scheme at CHAMPHUNGPHEDUkhrul91.000.00Others07/03/20232020-2021-In-ProgressView
2880UKL/NDB/TANRUI UPPERW/s scheme at TANRUI UPPERPHEDUkhrul131.000.00Others07/03/20232019-2020-In-ProgressView