Progress
 
 
Project Details
DAR-2024-000889
SE-I/DAR/23-24/IE-R1.18Salanthong Awang
Impvt of road on Salanthong Awang Leikai
09/11/2023
PWD
Imphal-East
80.00
16
State Plan
work completed
final phase
24.83413421,93.96394123
Impvt of Road - GSB, WBM & SDBC
Progress Update : 07/03/2025
work completed
final phase
ae4ied
24.83413421,93.96394123
24.8334164,93.9637107
0.083133849481284
16
impvt. of salanthong awang leikai road