Progress
 
 
Project Details
DAR-2024-000826
SHD/constn of Bank Building security bloc/183
COnstn of Bank building, Security personal block & staff qtr at Bungte chiru SD HQ
21/11/2023
PWD
Kangpokpi
120.00
0.00
State Plan
Completed
2023-2024
24.68257330069105,93.75921535491977
Bank Building, Security block, staff qtr
Progress Update : 27/07/2024
Completed
2023-2024
Sadarhills
24.68257330069105,93.75921535491977
24.6821374,93.7593422
0.050133223492224
0
Bank building, security block, staff quarter

Progress Update : 27/07/2024
Completed
2023-2024
Sadarhills
24.68257330069105,93.75921535491977
24.6823902,93.7593093
0.022462705163886
0
Bank building, security block, staff quarter

Progress Update : 27/07/2024
completed
2023-2025
Sadarhills
24.68257330069105,93.75921535491977
24.6828303,93.7589766
0.037395478908509
0
bank building, security block, staff quarter

Progress Update : 27/07/2024
Completed
2023-2024
Sadarhills
24.68257330069105,93.75921535491977
24.6829495,93.7591604
0.042196362679383
0
Bank building, security block, staff quarter

Progress Update : 27/07/2024
in progress
2023-2024
Sadarhills
24.68257330069105,93.75921535491977
24.6826891,93.7592207
0.012886824818347
0
bank building, security block, staff quarter

Progress Update : 27/07/2024
In progress
2023-2024
Sadarhills
24.68257330069105,93.75921535491977
24.6825419,93.7592374
0.0041422880414471
0
Banking building, security personal block, staff quarter