Progress
 
 
Project Details
DAR-2024-000820
SHD/Impvt of Wainem ring road 1.5 km/180
Impvt of road from Wainem ring road 1.5 km
19/01/2024
PWD
Kangpokpi
80.00
24
State Plan
in progress
2023-2024
24.681362031451624,93.76153278350864
Kutcha drain,GSB, WBM and PC
Progress Update : 27/07/2024
in progress
2023-2024
Sadarhills
24.681362031451624,93.76153278350864
24.6889257,93.7663348
0.97089908524838
24
kutcha drain, shingling, wbm, pc

Progress Update : 27/07/2024
In progress
2023-2024
Sadarhills
24.681362031451624,93.76153278350864
24.6889181,93.7676288
1.0417107059154
24
kutcha drain, shingling, wbm, pc

Progress Update : 27/07/2024
In progress
2023-2024
Sadarhills
24.681362031451624,93.76153278350864
24.6888384,93.7674719
1.0252198513843
24
kutcha drain, shingling, wbm, pc