Progress
 
 
Project Details
DAR-2024-000785
SE-I/DAR/23-24/IE-R1.43 Poiroutongba Village
Improvement of road at Poiroutongba Village
2023-11-09
PWD
Imphal-East
70.00
44
State Plan
100%
...
24.68376919,94.0221223
Improvement of road -
Progress Update : 2025-02-12
100%
...
thoikh07
24.68376919,94.0221223
24.6831833,94.02168
0.078997826775716
Approved
44
GSB, WBM, PC, etc...- BT completed

Progress Update : 2025-02-12
100
...
thoikh07
24.68376919,94.0221223
24.6828853,94.0218256
0.10274904266315
Approved
2025-03-18 06:59:41
se1pwd
44
GSB, WBM,PC,etc...

Progress Update : 2024-07-30
in progress
---
thoikh07
24.68376919,94.0221223
24.6837417,94.0131433
0.90715180829842
Approved
2025-02-05 10:49:40
se1pwd
44
Impvt of Road - WBM in progress

Foundation & Inauguration
-
-
-

-
-
-