Progress
 
 
Project Details
DAR-2024-000699
CCP/constn of drain at Upper Kom Keirap/140
Construction of drain at Upper Kom Keirap 2 Km
19/01/2024
PWD
Churachandpur
136.36
0.00
State Plan
62%
Phase 1
24.583417501971294,93.73560118675266
Pucca drain
Progress Update : 21/10/2024
62%
Phase 1
soccpr1
24.583417501971294,93.73560118675266
24.5827097,93.7338169
0.19682993621511
0
RCC Pucca drain

Progress Update : 21/10/2024
62%
phase 1
soccpr1
24.583417501971294,93.73560118675266
24.5825285,93.7365
0.13427615430052
0
RCC Pucca drain