Progress
 
 
Project Details
DAR-2024-000683
SPT/Intra village road at Phaibung Khunou/124
Impvt of intra village road at Phaibung Khunou village
13/10/2023
PWD
Senapati
75.00
22.5
State Plan
70% progress
1
25.395584784854123,94.35539531707798
GSB, WBM-I,II and PC
Progress Update : 08/02/2025
70% progress
1
eesptd
25.395584784854123,94.35539531707798
25.3831273,94.3622479
1.5467505926724
22.5
gsb,wbm,pc

Progress Update : 08/02/2025
70% progress
1
eesptd
25.395584784854123,94.35539531707798
25.3831242,94.3622686
1.547985568034
22.5
gsb,wbm,pc

Progress Update : 20/07/2024
50% completed
1
eesptd
25.395584784854123,94.35539531707798
25.3828599,94.3622446
1.5732871875031
0
gsb,wbmI,II and pc