Progress
 
 
Project Details
DAR-2024-000669
UKL/Impvt of Raisheo Jn to Phalee Ukhrul /110
Impvt of road from Raisheo Jn to Phalee village, Ukhrul district
13/10/2023
PWD
Ukhrul
140.00
35
State Plan
68% completed
Phase-I
25.14811,94.28357
Widening, slab culvert, retaining wall & RCC pipe culvert
Progress Update : 18/10/2024
68% completed
Phase-I
eeukld
25.14811,94.28357
25.1241576,94.2849453
2.666852836596
35
widening,kutcha drain,slab culvert and pipe culvert

Progress Update : 18/10/2024
68% completed
Phase-I
eeukld
25.14811,94.28357
25.133951,94.2842574
1.575852933256
35
widening,kutcha drain,pipe culvert and slab culvert.

Progress Update : 18/10/2024
68% completed
Phase-I
eeukld
25.14811,94.28357
25.136354,94.2856724
1.3241635037042
35
widening,kutcha drain,pipe culvert and slab culvert.

Progress Update : 18/10/2024
68% completed
Phase-I
eeukld
25.14811,94.28357
25.1364158,94.2850607
1.3089018994301
35
widening, kutcha drain,pipe culvert and slab culvert