Progress
 
 
Project Details
DAR-2024-000666
UKL/LM subdivision to Torah village Ukhru/107
Impvt of road from LM Subdivision to Torah village, Ukhrul District (9 km Phase-II)
10/11/2023
PWD
Ukhrul
115.00
80.50
State Plan
completed
Phase-II
25.15110,94.24944
Widening, Pipe culvert
Progress Update : 24/10/2024
completed
Phase-II
eeukld
25.15110,94.24944
25.1617782,94.2437813
1.3168272435194
0
widening and pipe culvert

Progress Update : 24/10/2024
completed
Phase-II
eeukld
25.15110,94.24944
25.1619311,94.2437727
1.3325463156836
0
widening and pipe culvert

Progress Update : 24/10/2024
completed
Phase-II
eeukld
25.15110,94.24944
25.1582808,94.2444931
0.94094347505077
0
widening and pipe culvert

Progress Update : 24/10/2024
completed
Phase-I
eeukld
25.15110,94.24944
25.1582775,94.2444376
0.94360062275464
0
widening and pipe culvert

Progress Update : 24/10/2024
completed
Phase-I
eeukld
25.15110,94.24944
25.1581898,94.2445136
0.93127308025723
0
widening and pipe culvert