Progress
 
 
Project Details
DAR-2024-000656
SPT/Impvt of road at Sirong/98
Impvt of road at Sirong
13/10/2023
PWD
Senapati
70.00
52.45
State Plan
completed
1
25.377052084669693,94.27776145935093
GSB, WBM-I II and PC
Progress Update : 09/02/2025
completed
1
eesptd
25.377052084669693,94.27776145935093
25.3717824,94.268172
1.1275754623903
52.45
gsb,wbm,pc

Progress Update : 09/02/2025
completed
1
eesptd
25.377052084669693,94.27776145935093
25.3727076,94.2672687
1.1595400124261
52.45
gsb,wbm,pc

Progress Update : 09/02/2025
completed
1
eesptd
25.377052084669693,94.27776145935093
25.3721463,94.2680933
1.1139753527775
52.45
gsb,wbmI,II and pc

Progress Update : 27/07/2024
In progress
1
eesptd
25.377052084669693,94.27776145935093
25.3766456,94.2782058
0.063524620417786
21
gsb,wbmI,II and pc

Progress Update : 27/07/2024
In progress
1
eesptd
25.377052084669693,94.27776145935093
25.3766847,94.2782254
0.061975445826149
21
gsb,wbmI,II and pc

Progress Update : 27/07/2024
75%
1
eesptd
25.377052084669693,94.27776145935093
25.3790383,94.2777686
0.22084760727706
21
gsb,wbmI,II and pc

Progress Update : 27/07/2024
75
1
eesptd
25.377052084669693,94.27776145935093
25.3722467,94.2682053
1.0987062170223
21
gsb,wbmI,II and pc

Progress Update : 20/07/2024
50% completed
1
eesptd
25.377052084669693,94.27776145935093
25.3779715,94.2778482
0.10260009537524
21
gsb,wbm1,2 and pc

Progress Update : 20/07/2024
50% completed
1
eesptd
25.377052084669693,94.27776145935093
25.3777161,94.2778308
0.074159434650722
21
gsb,wbm1,2 and pc

Progress Update : 20/07/2024
50% completed
1
eesptd
25.377052084669693,94.27776145935093
25.3777161,94.2778308
0.074159434650722
21
gsb,wbm1,2 and pc

Progress Update : 20/07/2024
50% completed
1
eesptd
25.377052084669693,94.27776145935093
25.3779715,94.2778482
0.10260009537524
21
gsb,wbm1,2 and pc