Progress
 
 
Project Details
DAR-2024-000610
KCG/DARPAN/ROAD(P)/71
Improvement of IVR in and around Tangjeng Khunou
09/11/2023
PWD
Kakching
62.31
12.5
State Plan
70% Completed
2nd phase
24.3171124120163,93.881446045166
road work
Progress Update : 12/08/2024
70% Completed
2nd phase
9774805717
24.3171124120163,93.881446045166
24.3172936,93.879412
0.20708152658767
12.5
GSB, WBM, Slab Culvert, Pipe Culvert