Progress
 
 
Project Details
DAR-2024-000568
SEIV/newcutting from Oklong to Gopinala/66
New cutting from Oklong road to Gopinala via katomei centre village 6km
05/01/2024
PWD
Senapati
200.00
0.00
State Plan
In progress
phase I
25.28257065822746,94.01859569549595
Formation cutting & 900mm diameter pipe culvert
Progress Update : 03/07/2024
In progress
phase I
eesptd
25.28257065822746,94.01859569549595
25.2865967,94.0081167
1.1446921493162
0
formation widening, pipe culvert

Progress Update : 03/07/2024
In progress
phase I
eesptd
25.28257065822746,94.01859569549595
25.2842333,94.008545
1.0272517747004
0
formation widening, pipe culvert

Progress Update : 03/07/2024
In progress
phase I
eesptd
25.28257065822746,94.01859569549595
25.2830582,94.0171718
0.15307691421025
0
Formation widening, pipe culverts