Progress
 
 
Project Details
DAR-2024-000554
SE-I/DRP/2023-24/R1-67 -Rongmei Khul
Improvement of road and drain at Chingmeirong Rongmei Khul
2023-02-23
PWD
Imphal-East
50.00
23
State Plan
completed 100 pc
---
24.831247,93.9458447
Improvement of road and drain - GSB WBM PC & CC works
Progress Update : 2025-02-19
completed 100 pc
---
yaiphabaIreng
24.831247,93.9458447
24.8315313,93.9488165
0.3015453250646
Approved
2025-02-19 12:19:23
se1pwd
23
Completed roadwork till blacktopping, drainage completed

Progress Update : 2024-07-03
completed
NA
thengra
24.831247,93.9458447
24.8313133,93.94908
0.32655706313193
Approved
2024-07-09 08:07:24
se1pwd
10
BT surface completed

Foundation & Inauguration
-
-
-

-
-
-