Progress
 
 
Project Details
DAR-2024-000496
D-IV/Y.K/CFM
Infrastructure development of Government college under COLLEGE FAGATHANSI MISSION for the year 2023-24 at Y. K. College,Thoubal, Manipur.
2023-10-20
Education (S)
Thoubal
250.00
94.05
CSS / CPS
completed
final
24.593838182857528,94.03723530052488
Infrastructure development of Government college under COLLEGE FAGATHANSI MISSION for the year 2023-24 at Y. K.College,Thoubal, Manipur. Part A & B
Progress Update : 2026-03-24
completed
final
ae.elect-eew
24.593838182857528,94.03723530052488
24.5942589,94.037349
0.048170962056174
Approved
2026-03-26 10:48:56
ee4.eew-mn
0
block B

Progress Update : 2026-03-24
completed
final
ae.elect-eew
24.593838182857528,94.03723530052488
24.5944454,94.0371307
0.068339445452003
Approved
2026-03-26 10:49:43
ee4.eew-mn
0
classroom b I E I

Progress Update : 2026-03-24
iei
completed
ae.elect-eew
24.593838182857528,94.03723530052488
24.5940538,94.0373118
0.025190831250342
Approved
2026-03-26 10:47:59
ee4.eew-mn
0
block b verendha

Progress Update : 2026-03-24
completed
final
ae.elect-eew
24.593838182857528,94.03723530052488
24.5940956,94.0373588
0.031227016139274
Approved
2026-03-26 10:50:44
ee4.eew-mn
0
block a iei

Progress Update : 2025-11-16
.
.
so9.eew
24.593838182857528,94.03723530052488
24.5932373,94.0369347
0.073399505296506
Approved
2025-11-20 10:44:03
ee4.eew-mn
0
.

Progress Update : 2025-11-16
.
.
so9.eew
24.593838182857528,94.03723530052488
24.5938452,94.0372639
0.0029944589467959
Approved
2025-11-20 10:54:31
ee4.eew-mn
0
.

Progress Update : 2025-06-21
.
.
so9.eew
24.593838182857528,94.03723530052488
24.5932898,94.0370259
0.064545287904493
Approved
2025-11-20 10:51:53
ee4.eew-mn
0
.

Progress Update : 2025-06-21
.
.
so9.eew
24.593838182857528,94.03723530052488
24.5937154,94.0373566
0.018351364946758
Approved
2025-11-20 10:49:56
ee4.eew-mn
0
.

Progress Update : 2025-01-12
The work has been complete upto roof beam
2nd
so9.eew
24.593838182857528,94.03723530052488
24.5938059,94.0371068
0.01347849231828
Approved
0
Construction of classroom .block A

Progress Update : 2025-01-12
The work has been complete upto slab
2nd .
so9.eew
24.593838182857528,94.03723530052488
24.5938778,94.0370308
0.02113951987485
Approved
0
Construction classroom block A & B

Progress Update : 2025-01-12
The work has been complete upto roof beam
2nd
so9.eew
24.593838182857528,94.03723530052488
24.5937528,94.0371934
0.010396540393953
Approved
0
construction of classroom block A

Progress Update : 2025-01-12
The work has been complete upto roof beam
2nd
so9.eew
24.593838182857528,94.03723530052488
24.5939741,94.0372779
0.015714405441622
Approved
2025-02-05 07:50:03
ee4.eew-mn
0
construction of classroom

Progress Update : 2025-01-03
The work has been complete upto slab
2nd .
so9.eew
24.593838182857528,94.03723530052488
24.5929248,94.0366352
0.11830144082475
Approved
0
construction of classroom ,Block B

Progress Update : 2025-01-03
The work has been complete upto slab
2nd .
so9.eew
24.593838182857528,94.03723530052488
24.5940503,94.0369741
0.035406871865909
Approved
0
construction of classroom bloc B

Progress Update : 2025-01-03
The work has been complete upto slab
2rd
so9.eew
24.593838182857528,94.03723530052488
24.5939149,94.0370166
0.023699623717317
Approved
0
construction of classroom Bloc B

Progress Update : 2024-07-29
The work has complete upto Roof beam
2023-2024
so9.eew
24.593838182857528,94.03723530052488
24.5959268,94.0359106
0.26808397969389
Approved
2024-09-02 08:43:48
ee4.eew-mn
0
construction upto roof beam side view for block -A

Progress Update : 2024-07-29
The work has complete upto Ground Roof beam
2023-2024
so9.eew
24.593838182857528,94.03723530052488
24.5938106,94.0373273
0.0097939809730419
Approved
0
Side view for block A

Progress Update : 2024-07-29
The work has complete upto Roof beam
2023-2024
so9.eew
24.593838182857528,94.03723530052488
24.5959218,94.0358993
0.26817613823538
Approved
2024-08-01 07:42:57
ee4.eew-mn
0
construction upto roof beam back view for Block -A

Progress Update : 2024-07-29
In progress
1st
so9.eew
24.593838182857528,94.03723530052488
24.5959286,94.0359107
0.26825232492858
Approved
2024-09-02 08:52:35
ee4.eew-mn
0
Back side view

Progress Update : 2024-07-29
Ground floor slab
2023-2024
so9.eew
24.593838182857528,94.03723530052488
24.5951541,94.0366646
0.157281972365
Approved
0
Back side view for photos is block -A

Progress Update : 2024-07-29
The work has complete upto Roof beam
2023-2024
so9.eew
24.593838182857528,94.03723530052488
24.5951541,94.0366646
0.157281972365
Approved
2024-08-01 07:43:33
ee4.eew-mn
0
Side view for block-A

Foundation & Inauguration
-
-
-

-
-
-