Progress
 
 
Project Details
DAR-2024-000492
D-IV/LILONG HAOREIBI/CFM
Infrastructure development of Government college under COLLEGE FAGATHANSI MISSION for the year 2023-24 at Lilong Haoreibi College,Thoubal, Manipur
2023-10-20
Education (S)
Thoubal
250.00
144.07
CSS / CPS
The work has been complete upto roofing
final
24.68430849412299,93.94956676455685
Infrastructure development of Government college under COLLEGE FAGATHANSI MISSION for the year 2023-24 at Lilong Haoreibi College,Thoubal, Manipur. Part A & B
Progress Update : 2025-07-26
The work has been complete upto roofing
final
so9.eew
24.68430849412299,93.94956676455685
24.6844793,93.9495607
0.019001566091158
Approved
2025-11-20 07:17:43
ee4.eew-mn
0
construction of classroom

Progress Update : 2025-07-26
The work has been complete upto roofing
3rd
so9.eew
24.68430849412299,93.94956676455685
24.6843978,93.9495287
0.010648333963635
Approved
2025-11-20 07:21:02
ee4.eew-mn
0
construction of classroom

Progress Update : 2025-07-26
.
.
so9.eew
24.68430849412299,93.94956676455685
24.6853147,93.9481367
0.18273179310869
Approved
2025-11-20 13:16:24
ee4.eew-mn
0
.

Progress Update : 2025-07-26
The work has been complete upto roofing
final
so9.eew
24.68430849412299,93.94956676455685
24.6846111,93.9497775
0.039816623745352
Approved
2025-11-20 07:22:42
ee4.eew-mn
0
construction of classroom For a

Progress Update : 2025-07-26
The work has been complete upto roofing
final
so9.eew
24.68430849412299,93.94956676455685
24.6853663,93.9481607
0.18442575904412
Approved
2025-11-20 07:29:20
ee4.eew-mn
0
construction of classroom block A & B verdra

Progress Update : 2025-07-26
The work has been complete for roofing
final
so9.eew
24.68430849412299,93.94956676455685
24.6853897,93.9481539
0.18662080266771
Approved
2025-11-20 07:15:30
ee4.eew-mn
0
construction of classroom block b in front view

Progress Update : 2025-07-26
The work has been complete upto roofing
final
so9.eew
24.68430849412299,93.94956676455685
24.6854466,93.9482702
0.1821325667613
Approved
2025-11-20 07:31:26
ee4.eew-mn
0
construction of classroom A

Progress Update : 2025-05-31
The work has been complete upto roofing
final
so9.eew
24.68430849412299,93.94956676455685
24.6854063,93.9482337
0.18176342133199
Approved
2025-11-20 07:26:22
ee4.eew-mn
0
construction classroom block a & b

Progress Update : 2025-01-03
The work has been complete upto Roof
2023-2024
so9.eew
24.68430849412299,93.94956676455685
24.685836,93.9487621
0.18829581596477
Approved
0
construction of classroom side view

Progress Update : 2025-01-03
The work has been complete upto Roof
2023-2024
so9.eew
24.68430849412299,93.94956676455685
24.6858386,93.9488595
0.1845278572608
Approved
2025-01-21 09:15:54
ee4.eew-mn
0
Construction of Classroom

Progress Update : 2025-01-03
The work has been complete upto Roof
2023-2024
so9.eew
24.68430849412299,93.94956676455685
24.6859075,93.9488992
0.19015480776532
Approved
2025-01-21 09:15:21
ee4.eew-mn
0
Construction of Classroom

Progress Update : 2025-01-03
The work has been complete upto Roof
2023-2024
so9.eew
24.68430849412299,93.94956676455685
24.6858167,93.9488791
0.18151813194488
Approved
2025-01-21 09:18:54
ee4.eew-mn
0
construction of classroom front view

Progress Update : 2025-01-03
The work has been complete upto Roof
2023-2024
so9.eew
24.68430849412299,93.94956676455685
24.6845954,93.9491921
0.049502075239989
Approved
2025-01-21 09:20:14
ee4.eew-mn
0
construction of class room side view

Progress Update : 2024-07-23
The work has been complete upto roof beam
2023-2024
so9.eew
24.68430849412299,93.94956676455685
24.6856425,93.9482432
0.1997037993166
Approved
2024-08-01 07:49:04
ee4.eew-mn
0
construction of college front view for block A

Progress Update : 2024-07-23
The work has been complete upto roof beam
2023-2024
so9.eew
24.68430849412299,93.94956676455685
24.6847425,93.949223
0.059455215822189
Approved
2024-08-01 07:58:40
ee4.eew-mn
0
construction college Front view for Block A & B

Progress Update : 2024-07-23
The work has been complete upto roof beam
2023-2024
so9.eew
24.68430849412299,93.94956676455685
24.6844066,93.9494054
0.019615546753372
Approved
2024-08-01 07:59:11
ee4.eew-mn
0
construction of college front view for block A & B

Progress Update : 2024-07-23
The work has been complete upto roof beam
2023-2024
so9.eew
24.68430849412299,93.94956676455685
24.684584,93.9498047
0.03893896102942
Approved
0
construction of college for block -A

Progress Update : 2024-07-23
The work has been complete upto roof beam
2023-2024
so9.eew
24.68430849412299,93.94956676455685
24.6844349,93.9498781
0.034451354832113
Approved
2024-08-01 07:55:04
ee4.eew-mn
0
Construction of college front view for block A

Progress Update : 2024-06-21
The work has been complete upto roof beam
2023-2024
so9.eew
24.68430849412299,93.94956676455685
24.6845506,93.9496607
0.028543541205192
Approved
2024-08-01 07:59:44
ee4.eew-mn
0
classroom fot block B

Progress Update : 2024-06-21
The work has been complete upto roof beam
2023-2024
so9.eew
24.68430849412299,93.94956676455685
24.6845506,93.9496607
0.028543541205192
Approved
2024-08-01 11:01:19
ee4.eew-mn
0
Construction of college block B

Foundation & Inauguration
-
-
-

-
-
-