Progress
 
 
Project Details
DAR-2024-000394
SE-I/BDG/DRP/2022-23/C1/393-5 30 ft BB R/W
Construction of 30 ft span Bailey Bridge over Thongjaorok river in between Bishnupur Ward No 5 & 7(SH: retaining Wall))
2022-10-12
PWD
Bishnupur
204.00
30
State Plan
Ongoing
Final
24.62394,93.758
Constn of BB Retaining Wall
Progress Update : 2025-03-06
Ongoing
Final
so1brd3
24.62394,93.758
24.6241996,93.7582529
0.03855683814804
Approved
2025-03-12 10:40:29
se1pwd
30
85.16 percentage completed

Progress Update : 2024-07-23
Ongoing
Middle phase
so1brd3
24.62394,93.758
24.6240245,93.7580821
0.012535889626696
Approved
2024-10-10 08:32:39
se1pwd
0
Two of four side completed

Progress Update : 2024-03-20
Ongoing
Middle
so1brd2
24.62394,93.758
24.6240898,93.7580739
0.018254367396047
Approved
2024-03-21 10:21:46
se1pwd
0
Retaining Wall

Foundation & Inauguration
-
-
-

-
-
-