Progress
 
 
Project Details
DAR-2018-000172
IED/Culvert-Ayangpalli Road/60
Constn. of 3.00m span RCC slab culvert at Ayangpalli Road.
2018-02-06
PWD
Imphal-East
58.08
0.00
State Plan
Completed
NA
24.79947786666464,93.95818591331408
Progress Update : 2018-03-13
Completed
NA
shibadatta
24.79947786666464,93.95818591331408
24.7993584,93.9582002
0.013361310630204
Approved
2020-02-07 10:33:45
se1pwd
0
Rcc slab culvert

Progress Update : 2018-03-13
Completed
NA
shibadatta
24.79947786666464,93.95818591331408
24.7993249,93.9582287
0.017548068152434
Approved
2018-03-13 10:33:37
ace3pwd
0
Rcc slab culvert

Progress Update : 2018-03-13
Completed
NA
shibadatta
24.79947786666464,93.95818591331408
24.7993042,93.9583383
0.024686918545599
Approved
2018-03-13 10:33:47
ace3pwd
0
Rcc slab culvert

Progress Update : 2018-03-13
Completed
NA
shibadatta
24.79947786666464,93.95818591331408
24.8075548,93.9521676
1.0842134834444
Approved
2018-03-13 10:33:55
ace3pwd
0
Rcc slab culvert

Foundation & Inauguration
-
-
-

-
-
-