Project Details
DAR-2024-000264
UKL/SE-IV/SP quarters to NH-102A mainbazar/15
Impvt. of PWD road SP Quarter to NH-102A main bazar ZEO Office area
2023-12-29
PWD
Ukhrul
6000000.00
0.00
State Plan
32% completed
2023-2024
25.098079913542993,94.36302888393436
GSB, WBM I&II, Cosed graded premix carpeting 2. Retaining wall 3. Pucca drain
Progress Update : 2024-07-19
32% completed
2023-2024
eeukld
25.098079913542993,94.36302888393436
25.0984077,94.3669535
0.39685167152952
Approved
0
gsb, wbm, line drain, retaining wall

Progress Update : 2024-07-19
32% completed
2023-2024
eeukld
25.098079913542993,94.36302888393436
25.0984139,94.3658449
0.28596965163636
Approved
0
GSB, WBM, P.C., line drain, retaining wall

Progress Update : 2024-07-19
32% completed
2023-2024
eeukld
25.098079913542993,94.36302888393436
25.0985314,94.3635703
0.074108500340892
Approved
0
GSB, WBM, P.C., retaining wall, lined drain

Progress Update : 2024-07-19
32% completed
2023-2024
eeukld
25.098079913542993,94.36302888393436
25.0978854,94.3625851
0.04964405254179
Approved
0
earth work, gsb, 900 mm pipe culvert, line drain

Progress Update : 2024-07-19
32% completed
2023-2024
eeukld
25.098079913542993,94.36302888393436
25.0975973,94.3623081
0.09026055594699
Approved
0
earth work in cutting, gsb, 900 mm pipe culvert, lined drain

Progress Update : 2024-07-19
32% completed
2023-2024
eeukld
25.098079913542993,94.36302888393436
25.0971823,94.3620867
0.13770051784416
Approved
0
earth work in cutting, gsb, 900 mm pipe culvert, line drain

Progress Update : 2024-07-19
32% completed
2023-2024
eeukld
25.098079913542993,94.36302888393436
25.0971823,94.3620867
0.13770051784416
Approved
0
earth work in cutting, gsb, 900 mm pipe culvert, line drain

Progress Update : 2024-03-20
32% completed
2023-2024
eeukld
25.098079913542993,94.36302888393436
25.0971656,94.3619572
0.14825551354905
Approved
0
GSB, WBM, P.C. 900 mm pipe culvet

Progress Update : 2024-03-20
32% completed
2023-2024
eeukld
25.098079913542993,94.36302888393436
25.0971376,94.3620744
0.14217866502149
Approved
0
GSB, WBM, P.C. 900 mm pipe culvet

Progress Update : 2024-03-19
32% completed
2023-2024
eeukld
25.098079913542993,94.36302888393436
25.096867,94.3619484
0.1732763060093
Approved
0
GSB, WBM-II, III & P.C. pucca drain

Foundation & Inauguration
-
-
-

-
-
-