Progress
 
 
Project Details
DAR-2024-000249
EE/BPR/Impvt Kakyal Mamang Chungkham IVR
Improvement of Kakyal Mamang via Chungkham IVR (SH-1 meter spanslab culvert)
2023-11-09
PWD
Bishnupur
100.00
37
State Plan
completed
Final
24.7171984,93.83603529999999
road
Progress Update : 2026-05-08
completed
Final
lalit
24.7171984,93.83603529999999
24.7134267,93.8736217
3.8194781208817
Approved
2026-05-08 07:20:30
se3pwd
37
GSB, WBM, PC

Progress Update : 2024-09-20
in progress 80pc
2nd phase
lalit
24.7171984,93.83603529999999
24.7131545,93.8729251
3.7530616244992
Approved
2024-10-14 08:00:39
se3pwd
20
gsb, wbm

Progress Update : 2024-03-19
In progress
1st phase
lalit
24.7171984,93.83603529999999
24.7075316,93.8736817
3.9515277057643
Approved
2024-10-14 08:02:09
se3pwd
20
Gsb, wbm

Foundation & Inauguration
-
-
-

-
-
-