Progress
 
 
Project Details
DAR-2023-000909
UPG 2022-2023 Moirangpurel HS(Sceince)
Construction of Upgraded High School to Higher Secondary under Samagra Shiksha (Secondary) 2023-24 at Moirangpurel High School,Imphal East, Manipur
24/08/2023
Education (S)
Imphal-East
233.79
91.21
CSS / CPS
The work has been complete upto slab
3rd
24.789788503973124,94.12595607521592
Construction of Upgraded High School to Higher Secondary under Samagra Shiksha (Secondary) 2023-24 at Moirangpurel High School, Imphal East, Manipur (Sh. Construction of 12 Rooms for Science, Part-I) (Sh.(i) Construction of 12 Rooms for Science, Part-II, (ii) Construction of Toilet Block, (iii) Construction of Septic Tank & Soak Pit & (iv) Construction of Rain Water Harvesting Structure (a) Construction of Water Tank with water Filteration Plant (b) Construction of Over Head Water Tank)
Progress Update : 20/01/2025
The work has been complete upto slab
3rd
so9.eew
24.789788503973124,94.12595607521592
24.78828,94.12611
0.16844807464021
0
Corridor view for construction of 12 classroom, Part-I

Progress Update : 20/01/2025
The work has been completed upto roof level
2nd
so9.eew
24.789788503973124,94.12595607521592
24.7883583,94.1259133
0.1590823792697
0
Inner view of Classroom, Part-II

Progress Update : 20/01/2025
The work has been completed upto roof level
2nd
so9.eew
24.789788503973124,94.12595607521592
24.78861,94.126115
0.13201574733335
0
Corridor view of Classroom, Part-II

Progress Update : 20/01/2025
The work has been complete upto slab
3rd
so9.eew
24.789788503973124,94.12595607521592
24.7885183,94.1258767
0.14146054961785
0
Perspective view of 12 classroom, Part-I

Progress Update : 20/01/2025
The work has been completed upto slab
3rd
so9.eew
24.789788503973124,94.12595607521592
24.7886219,94.1256936
0.13239250153678
0
Perspective view of Classroom, Part-I

Progress Update : 20/01/2025
The work has been complete upto roofing
Nill
so9.eew
24.789788503973124,94.12595607521592
24.7887031,94.1259134
0.12076248640472
0
Full view of Classroom-Science, Part- I & II

Progress Update : 25/05/2024
In progress
1st
so9.eew
24.789788503973124,94.12595607521592
24.7885,94.1258767
0.14349206209353
0
Front view

Progress Update : 25/05/2024
In
1st
so9.eew
24.789788503973124,94.12595607521592
24.7883196,94.1252927
0.17652141525743
0
Side View

Progress Update : 25/05/2024
In progress
2nd
so9.eew
24.789788503973124,94.12595607521592
24.7883196,94.1252927
0.17652141525743
0
Side View

Progress Update : 25/05/2024
In progress
2nd
so9.eew
24.789788503973124,94.12595607521592
24.7887641,94.1260598
0.11438321864516
0
Front View