Progress
 
 
Project Details
DAR-2023-000892
IED/Return Wall-Top Khongnangkhong Bridge/862
Contn. of Return Wall at Top Khongnangkhong Bridge, Kshetrigao A/C, Imphal east
2023-11-09
PWD
Imphal-East
27.88
5.6
State Plan
Completed
--
24.806691477741737,93.98051542209014
Progress Update : 2024-07-09
Completed
--
mstqahmed7
24.806691477741737,93.98051542209014
24.8057587,93.9802701
0.1066297783678
Approved
2024-07-17 02:32:54
se1pwd
5.6
RR Return Wall completed

Foundation & Inauguration
-
-
-

-
-
-