Progress
 
 
Project Details
DAR-2018-000125
BD-II/T-VII/E-1/NP/2017-18/1
Major repairing of Qtr. no. T-VII/E-1 at Lamphelpat
16/05/2017
PWD
Imphal-West
20.01
20.01
State Non-plan
100%
1
24.82002325807509,93.92249214649223
Door and windows replacements, ceiling replacement, plastering, CGI sheet repairing, flooring etc.
Progress Update : 29/01/2018
100%
1
so1bd2
24.82002325807509,93.92249214649223
24.819926,93.9225784
0.01388230079742
0
Qtrs repairing, ceiling replacement, plastering, doors and windows replacement, CGI sheet repairing, painting, flooring etc

Progress Update : 29/01/2018
100%
1
so1bd2
24.82002325807509,93.92249214649223
24.8199255,93.9225753
0.013731854045594
0
Qtrs repairing, ceiling replacement, plastering, doors and windows replacement, CGI sheet repairing, painting, flooring etc

Progress Update : 29/01/2018
100%
1
so1bd2
24.82002325807509,93.92249214649223
24.8199258,93.9225755
0.013718065391964
0
Qtrs repairing, ceiling replacement, plastering, doors and windows replacement, CGI sheet repairing, painting, flooring etc

Progress Update : 29/01/2018
100%
1
so1bd2
24.82002325807509,93.92249214649223
24.819926,93.9225767
0.013775427061568
0
Qtrs repairing, ceiling replacement, plastering, doors and windows replacement, CGI sheet repairing, painting, flooring etc

Progress Update : 29/01/2018
100%
1
so1bd2
24.82002325807509,93.92249214649223
24.8199251,93.9225754
0.013773464330624
0
Qtrs repairing, ceiling replacement, plastering, doors and windows replacement, CGI sheet repairing, painting, flooring etc

Progress Update : 29/01/2018
100%
1
so1bd2
24.82002325807509,93.92249214649223
24.8199258,93.9225753
0.01370590675165
0
Qtrs repairing, ceiling replacement, plastering, doors and windows replacement, CGI sheet repairing, painting, flooring etc

Progress Update : 29/01/2018
100%
1
so1bd2
24.82002325807509,93.92249214649223
24.8229188,93.9194284
0.4463753486997
0
Qtrs repairing, ceiling replacement, plastering, doors and windows replacement, CGI sheet repairing, painting, flooring etc