Progress
 
 
Project Details
DAR-2023-000519
SPT/DAR/2022-23/R2/344-14 Pisgah College
lmpvt. of road from Mt. Pisgah College to Shomai Taheizang Sadbhavna Mandap Community Hall Senapati Dist HQ
23/02/2023
PWD
Senapati
150.00
84
State Plan
completed
phase 1
25.26899,94.03591
Hill cutting, Ring culvert, Slab culvert
Progress Update : 05/09/2024
completed
phase 1
eesptd
25.26899,94.03591
25.2690033,94.03339
0.25339096177819
84
hill cutting, katcha drain, slab and pipe culvert

Progress Update : 05/09/2024
completed
phase 1
eesptd
25.26899,94.03591
25.2635883,94.0322052
0.70676158444477
84
hill cutting, katcha drain, slab and pipe culvert

Progress Update : 05/09/2024
completed
phase 1
eesptd
25.26899,94.03591
25.2626987,94.0320034
0.802275145188
84
hill cutting, katcha drain, slab and pipe culvert

Progress Update : 28/03/2023
In progress
First
eesptd
25.26899,94.03591
25.2642783,94.0310433
0.71689152905265
0
Formation in Hill cutting

Progress Update : 28/03/2023
In progress
First
eesptd
25.26899,94.03591
25.2642442,94.0299885
0.79559716252825
0
Formation - Hill cutting

Progress Update : 28/03/2023
In progress
First
eesptd
25.26899,94.03591
25.2619283,94.028425
1.0876521294628
0
Formation cutting