DAR-2023-000329
CCP/DAR/2022-23/Rd2/375-16 Zomi Colony Ccpur
Impvt. of road in and around Zomi Colony Ccpur
2023-02-23
PWD
Churachandpur
150.00
75
State Plan
Completed
2022-23
24.34714,93.69721
GSB, WBM and PC & SC
Progress Update : 2024-07-25
Completed
2022-23
soccpr1
24.34714,93.69721
24.3477011,93.6993033
0.22103988169898
Approved
75
GSB,WBM,PC

Progress Update : 2024-07-24
Complete
2022-23
soccpr1
24.34714,93.69721
24.3471256,93.6967355
0.048093916851643
Approved
75
GSB, WBM, PC

Progress Update : 2023-03-27
Ongoing
2022-23
soccpr1
24.34714,93.69721
24.3470315,93.6966304
0.059940619405114
Approved
75
WBM in progress

Progress Update : 2023-03-25
Ongoing
2022-23
soccpr1
24.34714,93.69721
24.3470148,93.6967443
0.049186853619142
Approved
2025-03-24 11:52:33
pwdse2ce
75
Road work

Foundation & Inauguration
-
-
-

-
-
-