Progress
 
 
Project Details
DAR-2023-000323
KMJ/DAR/2022-23/Rd2/309-6 Chingsou Village
Impvt. of road from PMGSY to Chingsou village
23/02/2023
PWD
Kamjong
140.00
0.00
State Plan
In progress
Phase 1
24.7583,94.2202
Hill cutting in Formation widening, RCC Pipe Culvert & Protection Works
Progress Update : 25/03/2023
In progress
Phase 1
je1kamjongdiv
24.7583,94.2202
24.758485,94.2207468
0.058917425480559
0
Earthwork in formation widening

Progress Update : 25/03/2023
In progress
Phase 1
je1kamjongdiv
24.7583,94.2202
24.7583203,94.2202092
0.0024425070039943
0
Earthwork in formation widening

Progress Update : 25/03/2023
In progress
Phase 1
je1kamjongdiv
24.7583,94.2202
24.7582604,94.2201862
0.004617577499346
0
Earthwork in formation widening