Progress
 
 
Project Details
DAR-2023-000302
KCG/DARPAN/ROAD(P)/43
Impvt. of road of Hiyanglam Lai Pangalba to Terapishak School Angangba and 2cm span slab culvert at Terapishak Khongnangkhong Keithel over canal and
2023-02-23
PWD
Kakching
115.00
71.72
State Plan
100 pc
3rd phase
24.530189902255604,93.91744430172729
WBM PC Slab culvert
Progress Update : 2024-08-24
100 pc
3rd phase
9774805717
24.530189902255604,93.91744430172729
24.526748,93.9252787
0.88005894657275
Approved
2026-03-23 09:26:52
se3pwd
71.72
slab culvert, WBM, PC

Foundation & Inauguration
-
-
-

-
-
-